The following table and description refer to questions 83 through 89.
A project manager is using the earned value reporting method to manage his project. The following table shows the data collected to date. The plan is for the project to be complete after eight weeks. The earned value report shows data collected for the first four weeks of the project.
The figure shown in the table are cumulative.
Week PV AC EV
1 1,000 1,000 1,000
2 3,000 2,000 2,500
3 5,000 5,000 6,000
4 7,000 9,000 7,000
5 13,000
6 17,000
7 19,000
8 20,000
What is the EAC at week 4?
a. 20,000
b. 15,555
c. 25,714
d. 17,717
C
25,714