A preliminary delineation of roles and responsibilities, outlines the project objectives, identifies the main stakeholders, and defines the authority of the Project Manager.
What is Project Charter?
True or false: The Project Charter is an input for the Planning Process Group.
What is True?
This is an output of the Perform Integrated Change Control process, which can be a corrective action, a preventive action, or a defect repair.
What are Approved Change Requests?
This is the progress against the scheduled baseline and the computed time estimated to complete (ECT).
What is Schedule Forecasts?
This is the process of finalizing all actives across all the project management process groups to formally complete the project or phase.
What is the Closing Process?
The main tools of the Initiating process group.
What is Expert Judgement and Facilitation Techniques?
All the subsidiary plans and baselines for a project.
What is Project Management Plan?
This is used to discuss and address pertinent topics of the project.
What are Meetings?
This is the progress against the cost baseline and computed time (ETC).
What is Cost Forecasts?
This is the deliverable from the result of completing the entire project/phase.
What is the Final Product, Service, or Result Transition?
The written description of the project's product or service. This is supplied by the customer, but if the customer is your own organization then the project's sponsor will supply this document.
What is Project Statement of Work (SOW)?
If you need extra resources to develop your project management plan, you would look here.
What is PMBOK Book?
This is the performance data collected from various controlling processes, analyzed in context, and integrated based on relationships across areas.
What is Work Performance Information?
This provides the necessary data to confirm the change was appropriately executed.
What are Validated Changes?
This is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational project assets, project documents, and the project management plan; and communicating their disposition.
What is Integrated Change Control?
What is the main task for having the Initiating process group?
What is develop project charter?
This skill is used to tailor the process to meet project needs, and determines the skill levels needed for a project.
What is Expert Judgement?
A system that has access to a scheduling tool, work authorization, configuration management, information collection and distribution, and interfaces to other online automated systems.
What is the Project Management Information System?
These are techniques used to forecast potential outcomes based on possible variations of projects by regression analysis, grouping methods, and casual analysis.
What are Analytical Techniques?
Manual or automated tools will be used based on different needs, which manage change requests and the resulting decisions.
What is Change Control Tools?
This document explains why he project is being undertaken, considering the benefit of it and the cost analysis.
What is Business Case?
The final output of the Planning process group.
The most important output of this process group.
What is a Deliverable?
These are physical, as well as electronic, representations of work performance for project team members to bring change or awareness.
What are Work Performance Reports?
A documentation of changes encountered during a project, which impact the project in terms of time, cost, and risks, are communicated to the appropriate stakeholders.
What is a Change Log?