A
B
C
D
E
100

Computer-based system that accepts and processes data and produces information for users

What is an information system (IS)?

100

Technique of breaking down certain tasks into smaller units to try to fit them into the project plan, particularly when a project has a set of activities that are repeated several times

What is laddering?

100

This visualizes the sequential and logical relationships between tasks in a project setting

What is a network diagram?

100

What you plan to achieve by the end of the project, such as deliverables and assets

What is an objective?

100

Attainable, time-bound, specific goals you can measure at the end of the project, such as expected benefits, deliverables, date by which the project is required to be completed and the budget

What are project objectives?

200

An outline of the entire project, including any deliverables and their features as well as stakeholders who will be affected

What is a project scope document?

200

The common understanding among stakeholders about what goes into a project and what factors define its success

What is project scope? 

200

Project-specific plan that describes the activities, standards, tools and processes necessary to achieve quality in the delivery of a project

What is a project quality plan?

200

Chart that maps out every tasks, milestone or key decision and assigns which roles are responsible for each action item

What is a responsibility assignment matrix (RAM)?

200

Framework that describes the activities performed during each phase of a systems development project

What is a systems development life cycle (SDLC)?

300

Hierarchical tree structure that outlines the project and breaks it down into smaller, more manageable portions

What is a work breakdown structure (WBS)?

300

Group of related tasks within a project

What is a work package?

300

These define the functional, operational and performance specifications or capabilities that must be met for the project's end product and other project deliverables

What are customer requirements?

300

Formal document that defines the entire scope of the work involved for a vendor and clarifies deliverables, costs and timeline

What is a statement of work (SOW)?

300

Products or outputs that the project team or contractor will produce and provide to the customer during and at the completion of the performance of the project

What are deliverables?

400

The three most common techniques of network diagramming

What are program evaluation and review technique (PERT), critical path method (CPM), and precedence diagramming method (PDM)?

400

An illogical relationship among activities in a network diagram

What is a loop?

400

The systematic arrangement of tasks to accomplish an objective

What is planning?

400

Business document that announces and provides details about a project, as well as solicits bids from contractors

What is a request for proposal (RFP)?

400

A defined piece of work that consumes time

What is an activity?