Vocab
Vocab 2.O
Scenarios
vocab easy
Mystery
100

a graphical tool used for scheduling activities in a project plan. 

Precedent Diagram Method

100

Activity Resource Requirements is an input to which of the following processe

Estimate Activity Durations

100

Your task is to set up a set of high-end servers in a data center.  You are very familiar with the process since you have set up 6 other similar data centers for the organization.   Which techique will you use for determining the project time line?

Analogous

100

A method of estimating project duration
or cost by aggregating the estimates of
the lower-level components of the Work
Breakdown Structure (WBS).

Bottom-Up Estimating

100

What is the term for an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level

Rolling Wave Planning

200

used to perform Schedule Network Analysis that considers task dependencies, limited resource availability, and buffers.

Critical Chain Method

200

Reserve Analysis involves

Incorporating time buffers into the activity duration estimates

200

Your team is reviewing the project activities and has started to estimate the duration of the work packages identified in the WBS. Some of these work packages and activities have significant uncertainty associated with them for which the team has created contingency buffers. The tool and technique that is used for this process is called:

Reserve analysis

200

Used to help plan, organize,
and manage resource pools
and develop resource
elements.

Project Management Software

200

The blueprints for the new construction projects have been completed and construction is ready to begin. While the organization was thinking about erecting a modular structure, they decided on a more traditional approach. The foundation will be poured and cured before the framing begins. This is an example of:

Mandatory dependency

300

a business planning and modeling technique used to yield various projections for some outcome based on selectively changing inputs

What-if Scenario Analysis

300

Reserve Analysis involves

ncorporating time buffers into the activity duration estimates

300

"You are managing a construction project. You are currently estimating the duration of a very critical activity. You have gathered the following information from the experts:
Best case scenario: Activity can take 3 days to complete.
Worst case scenario: Activity may take up to 12 days to complete.
Likely scenario:  6 days to complete such activities.

Using Three-Point Analysis, what is the expected time?

7 days

300

Uses information from similar projects to
establish a cost estimate based on the
data available.

Analogous Estimating

300

Jasmine is very excited as she will be having her own apartment soon. She is just waiting for the day when she will get possession of her new home. However, she cannot start interior work unless the builder hands over keys of home after completion of electricity work. What kind of logical relationship can be said between these two activities?

Finish-to-Start

400

a technique used in project management to shorten an already developed schedule.

Schedule Compression

400

Reserve Analysis is a technique for

Estimate Activity Durations

400


if you're building a house, you
would have several task sequences as follows:
Each task takes a different amount of time and
resources. It takes more time to build walls and
lay the roof than to install faucets and fixtures.

Critical Path Method

400

uses a statistical relationship between
historical data and other variables (e.g.,
square footage in construction) to
calculate an estimate for activity
parameters, such as cost, budget, and
duration.

Parametric Estimating

400

your organization wants to launch a soft drink in the market. You are working as a project manager for the project. It is one of the important activities to get ‘pass’ certificate from the government’s food and drinks safety department. It will be illegal to launch the soft drink without obtaining safety certificate from government. What type of dependency is identified in this activity?

Mandatory dependencies

500

a technique where activities that would have been performed sequentially using the original schedule are performed in
parallel.

Schedule Fast tracking

500

What is project management 

the discipline of applying specific processes and principles to initiate, plan, execute and manage the way that new initiatives or changes are implemented within an organization.

500

Over-time.
Allocating additional resources to
specific activities. Hiring additional
resources.

schedule Crashing

500

used in management and information
systems applications for the
construction of an approximate
probability distribution representing the
outcome of future events, based on very
limited information.

Three-point estimates

500

Project schedule network diagram is an important output of which of the following processes?


Sequence activities