This Form is used for the "Facilities Engineering Work Request"
DA Form 4283
This fund is used for a new building project
MILCON funds
List 1 of the 3 "Higher-level" points of contact
1 - Design Agent.
2 - Regional Facility Director
3 - The SRM Guide
The planning that begins with the "move in" date as the final milestone is known as
Backward Planning
This form is used to transfer an ECN item off of the Hand Receipt
DA 3161
This AR covers "Army Facilities Management", has 483 pages and can help with "Master Planning"
AR 420-1
this fund is used the renovation or reconstruction of an existing building
O&M
List 2 of the 5 "Primary" points of contact
1 - Medical Activity Facility manager
2 - Contractor
3 - radiation protection officer, information management office etc.
4 - Garrison points of contact
5 - Medical Maintenance
Name 1 of the 2 "time" related planning steps and 1 was stated to be optional
1 - Identify time lines involved
2- Formulate a personalized backward plan or time line, optional
What are 3 of the 5 Dental laboratory considerations regarding equipment
1 - Ventilation hoods
2 - Natural gas
3 - Compressed air
4 - Specialized equipment
5 - Plumbing
This program guide will provide you with you need to know regarding the Planning of New Dental Facilities, to include the MIL-STD-1691 Military Medical and Dental Facilities publication.
SRM Program Guide UFC 4-510-1
How many project funds limits are there
4
The NCO should coordinate through this office before directly contacting the contractor
Project Office
This diagram is important when it comes to construction of a new or existing dental clinic
Floor Plan
What Form is used to transfer existing equipment off of the Hand Reciept
DA Form 3161
The AR covers the "Army Modification Program" and is 36 pages long.
AR 750-10
What is the lowest project fund limit
< $25,000
The name of the 2 "sheet(s)" needed in order to assist the project officer with procurement of all new equipment and furniture
1 - Data Sheets
2 - Cut Sheets
Who is responsible for demonstrating how to leverage certain design modifications based upon projected clinic business practices
NCOIC
What are 2 things that must be managed when moving from one clinic to another
1 - Manage movement of staff
2 - Manage movement of property and equipment
3 - Ensure all agencies are informed to include contractors, union representatives, ect.
4 - Manage staff training on any and all new equipment
What does (SRM) stand for in, SRM Program Guide UFC 4-510-01
Supplier Relationship Management
What is the largest project fund limit
>$750,000
This report will help to identify pre-existing equipment that could be used and will provide Maint. Cost(s) remaining on specific equipment
Equipment Replacement Report
Name 3 of the 4 clinic business practices one would need design modifications based upon
1 - First term dental readiness
2 - Dental clinic optimization
3 - Centralized sterilization
4 - Information management (IM) Information technology (IT)
What is the last thing to be completed after the move but prior to start of business
Ensure equipment and systems are functioning properly at the portable buildings(trailers) o rat the new or modernized facility as applicable.