Foreman
Foreman
Foreman
Foreman
Foreman
100

What is the most common reason for back charges?

A. Clean up B. Hoisting C. Material handling D. Scaffolding

Clean up

100

Submittals are for:

A. Tools B. Pay requests C. Equipment and material D. Safety inspections

Equipment and material

100

What does OSHA stand for?

Occupational Safety and Health Administration

100

When is personal cell phone use permitted?

A. Anytime B. During scheduled lunch and breaks C. Never during work hours D. Once every hou

During scheduled lunch and breaks

100

What should ALWAYS be your first priority in planning?

A. Making money B. Safety C. Keeping the crew busy D. Ordering material

Safety

200

You have a crew member who was late this morning for the 2nd time this week. How should you handle it?

n private, issue a warning

200

What is the standard regarding substance abuse?

Zero tolerance

200

What percentage of baby boomers will be eligible for retirement by 2017?

A. 64% B. 54% C. 14% D. 24%

14%

200

What is the average market share for UA Signatory Contractors?

A. 10-15% B. 25-30% C. 70-75% D. 15-20%

10-15%

200

What does CBA stand for?

Collective Bargaining Agreement

300

Who has the responsibility for accurate labor reporting?

A. Journeyworker B. Apprentice C. Foreman D. Project manager

Foreman

300

What is the purpose of a job completion checklist? 

A. To submit to the general contractor B. To place in your job files C. To assist the foreman in assuring the job is complete D. To submit with the billing for retention

To assist the foreman in assuring the job is complete

300

What is the minimum ratio of active workers to retirees?

A. 2 workers to every 1 retiree B. 1 worker to every 1 retiree C. 1 worker to every 2 retirees D. 1 worker to every 3 retirees

2 workers to every 1 retiree

300

The Standard for Excellence speaks to three groups. Who are they?

Members, local unions, employers

300

When should Pre-Construction Planning occur? 


Before the job begins

400

What is the best example of Ineffective Operations?

 A. Supervision, planning and tool-related activities B. Late start/early finish C. Personal telephone calls and chit chat with crew members D. Actually installing the work

Personal telephone calls and chit chat with crew members

400

Which of the following pieces of information does NOT need to be included on a daily log?

 A. Date B. Weather conditions C. Work done by individual crew members D. Deliveries

Work done by individual crew members

400

When is it permissible to make negative comments about your project manager or employer?

Never

400

What is the percentage of profit most contractors make before taxes? 

A. 10-15% B. 20-25% C. 5-10% D. 3-5%

3-5%

400

What is the most important piece of job site documentation?

Daily log

500

What is gross margin? 

A. Profit B. Difference between the dollar amount of the contract and the direct cost of doing the work C. Difference between estimated and expended labor D. Amount of markup on subcontractor costs

Difference between the dollar amount of the contract and the direct cost of doing the work

500

If your company is the prime contractor, what subcontractors are you required to manage?

All subcontractors

500

If your job has a productivity factor of .80 what does this indicate?

A. You are 20% over budget B. You are 20% under budget C. You are 20% ahead of schedule D. You are 20% behind schedule

You are 20% under budget

500

According to project owners around the country, was an area of concern about union construction?

A. Craftsmanship B. Training programs C. Ability to provide manpower D. Productivity

Productivity

500

What does the total cost of a labor hour include? 

 

Hourly wage, fringe package, payroll taxes, insurance, safety costs and small tools and consumables