Load control involves maintaining both the stability and this, of the load.

Orientation 

100

Before being stored, all rigging equipment should be

Clean and Dry

100

This is one of the most versatile knots. It forms a loop that is fixed in size at the end of the rope.

Bowline

100

One finger extended outward from the side

Swing

100

This is the assembly of components that connect a load to the lifting hook

Rigging 

200

The strength of a chain and chain attachments depend on the these, from which they are made.

Steel Alloys

200

Lift planners should be this

Qualified 

200

When should fiber ropes be inspected

Before each use

200

Both fists at the waist with thumbs pointing outward

Extend Telescoping Boom

200

The combination of ropes used with blocks to gain mechanical advantage 

Tackle

300

To determine whether the equipment remains within allowable specifications, some inspections may require the use of this...

Measuring Tools

300

This should always be the determining factor for the load rating of a roundsling

Identification Tag

300

This category of knots are used to tie the ends of two ropes together

Bend

300

A fist tapping the head

Use Main Hoist

300

A "dry run" of an actual lift is called this

Pre-lift Check 

400

This load is one in which half of the load is a mirror image of the other half

Symmetrical 

400

If hardware is found to have significant damage, it must be

Removed from service

400

A round turn is typically finished with two half hitches, which forms this

Clove Hitch

400

One hand clasped over the other

Dog Everything

400

As the load is lifted higher, the fall zone should be made

Larger

500

The distance from the cup of a hoist's top hook to the cup of the hoist hook when it is at its upper limit of travel is referred to as

Headroom

500

These loads always tilt towards the center of gravity 

Unbalanced 

500

Fiber rope should be derated when using these

Sheaves (Pulleys)

500

Hand extended toward the side with thumb pointing up and flexing fingers 

Raise the boom, lower the load

500

This person is required if the lift needs equipment or procedures that are unusual and do not conform to established standards