100

Name one of the 5 phases of project management

What is 

Project Initiation

Project planning 

Project execution

Project monitoring 

Project closing 

100

Utilized to determine ownership of a tract of land

What are title records?

100

Comprised of North-South Lines called meridians and East -West lines called base lines. 

What is the rectangular survey system

100

Title that is free from any encumbrances and any doubt to its validity

What is Marketable Title

100

If your project is planned to cross a federal or state highway you will likely need one 

What is a highway permit? 

200

Defining project goals, completing a project charter and identifying stakeholders. 

What is the project initiation 

200

Both Civil and environmental , these activities are typically the activities requiring access

What are Survey Records? 

200

Type of property description where a tract of land is irregularly shaped. (used extensively in Texas and California) 

What is metes and bounds

200

Chronological history of all the documents affecting a property 

What is Chain of Title? 

200

These permits are often categorized into two categories; crossing permits and parallel encroachment or longitudinal permits 

What are Railroad crossing permits

300

Specific, Measurable, Attainable, Realistic, Timely

What are SMART goals?

300

Detailed records of all contacts and communications with property owners

What are property contact records or parcel diaries. 

300

Two basic categories of Surveys 

Civil and Environmental surveys

300

The most common method to transfer ownership 

What are deeds? 

300

Federal Land Use Permits in the US are typically issued by these agencies 

Who are the US Forest Service and the Bureau of Land Management?

400

Completion of tasks and deliverables

What is project execution?

400

Records associated with Land Surveys 

What are Land Survey Records

400

These maps display individual tax parcels

What are tax maps 

400

Something in the chain of title that prevents one from having a clear title to property 

What is a title defect 

400

This Federal agency regulates all activities in US waters, including costal zones, navigable waters, streams and wetlands. 

Who is the US Army Corps of Engineers? 

500

The most critical task of Project Scope for a Transmission line

What is Route Selection 

500

The first step in the survey process 

What is Survey permission or right of entry. 

500

This mapping tool greatly expedites the selection of preferred or alternative routes as well as finding location-based information

What is GIS 

500

Quitclaims, Releases, satisfaction of judgements, subordinations

What are curative tools 

500
A closely related function of the permit acquisition process identifying and notifying other utilities to be impacted by the route. 

What is conflict review, joint use, or consent 