This is the wind speed cut off for nacelle hoisting.
12 m/s
This is where to complete a Safety Oberservation
Forms - Work Observation
Quick Link - Record Work Observation
This is the form that needs completed after an incident onsite by each employee
Witness Statement G0110P1AM01WI02F01
6 foot
Name 4 items that must be wore while working inside the tower.
Work Clothes, safety footwear, helmet with chin strap, gloves, transparent glasses, harness, sliding fall arrest device, safety lanyards, light, positioning lanyard, carabiners
This is where you complete annual training.
My Training
This is how soon you should report an incident onsite
Immediately
This is required for entering an energized tower
How Many people can be connected to a personal anchor point
Monthly for changes and updates as part of your PPE checks.
Reporting Truck Damages for 2023, How many will be reported?
All of them!
This is what and where you fill out for monthly truck inspections
Go Formz, through the link provided by Management
This is the document for wind farms under construction and commissioning.
IS0012
This is stored in EHS and is a document which helps analyze a new task or a task without instruction
Risk Assessment
What is All of the truck Damages?
0!!!
This is animal commonly attacking our trucks
Rabid Attacking Deer
These are the 5 Golden Rules of Electrical Safety
Interlocking or lockout of cutoff devices
Verify absence of Voltage
Ground and Short Circuit
Sign post the work Area
This was last weeks winner of Safety Walks performed
Magenta Wind Farm
This is where you submit HSE Incidents
Service Now
What is required for entering the hub of a tubine
Loto form
Loto locks and tags
Appropriate Wind Speeds