Reports
Field Safety
Calculations
Budgeting
CP Equipment
100

What are the three key parts of a corrosion project report?

Summary, field observations/data, and recommendations

100

What is a JSA used for?

To identify job steps, hazards, and safety precautions

100

Calculate Ireq: E_native = -600, E_off = -790, I_test = 2.0 A

Ireq = [(-850 - (-600)) × 2.0] / (-790 - (-600)) = (250×2) / -190 = -500 / -190 = 2.63 A

100

What is a Gantt chart used for?

To visualize project scheduling and task dependencies

100

What does a rectifier do?

Converts AC power to DC for CP current

200

Why is it important to include site photos in a field report?

Provides visual evidence and context for reported findings

200

Name one common jobsite hazard.

Tripping hazards, energized equipment, confined spaces, etc.

200

Estimate cost: 100 hrs @ $40/hr + $3,100 materials

$4,000 + $3,100 = $7,100

200

How do you estimate labor cost?

Multiply hours worked by hourly wage rate

200

Define a coating holiday.

A gap or defect in a protective coating exposing the metal

300

What section summarizes environmental conditions?

Field observations or environmental overview

300

Why is PPE necessary during CP testing?

Protects against shock, arc flash, environmental exposure

300

What does E_off mean in CP testing?

It's the instant-off potential measured when current is interrupted, used to assess polarization

300

Define budget overrun. Define budget overrun.

When project costs exceed the planned budget

300

What does a reference electrode measure?

Structure-to-electrolyte potential

400

Which report section includes voltage readings?

Data or measurement section

400

Who is responsible for identifying hazards?

Everyone on the job site (including the technician)

400

What tool is used to record voltage?

Multimeter or high impedance voltmeter

400

Why is time tracking important?

Ensures accurate billing, cost control, and deadline monitoring

400

What is a test station used for?

To monitor CP system voltage and currents

500

How do report errors affect project outcomes?

They can lead to safety issues, incorrect decisions, budget impacts, or regulatory noncompliance

500

What is one benefit of daily field documentation?

Helps track safety, technical issues, and protects against liability

500

Explain the formula: Ireq = ΔE × I_test / ΔV

It calculates the required CP current based on target potential shift and measured polarization

500

What data helps forecast project delays?

Task durations, resource availability, and progress metrics (e.g., Gantt updates)

500

Name one type of CP system.

Impressed current system or galvanic/anode-based system