You are managing a 6 month project and have held bi weekly meetings with yoru project stakeholders. After 5.5 months of work, the project is on schedule and budget, but the stakeholders are not satisfied with the deliverables. The sitation will delay the project completion by a month. the MOST important process that could have prevented this situation is?
Risk monitoring and control, schedule control, scope planning, or scope control
What is Scope Planning
The other choices are in monitoring and controling process group. This situation asks how to prevent the problem.