Scope Outlast Long Lasting Mint
I Scope A Winner
Name that U.S. Scope Creep
Words That End in "cope"
Automatic Points
100
Completion of a product scope is measured against: A. Product Management Plan B. Project Management Plan C. WBS & WBS Dictionary D. Product Requirements
What is C.WBS & WBS Dictionary
100
A new project manager has asked you for advice on creating a work breakdown structure. After you explain the process to her, she asks you what software she should use to create the WBS and what she should do with it when she is finished creating it. You might respond that it is not the picture that is the most valuable result of creating a WBS. It is: A. A bar chart B. Team buy-in C. Activities D. A list of risks
What is B. Team buy-in
100
8) You’ve just completed the Collect Requirements process. Which Scope Management process would you implement next? a) Plan Scope b) Define Scope c) Create WBS d) Scope Planning
What is b) Define Scope
100
All of the following are parts of the scope baseline EXCEPT the: A. Scope management plan B. Project scope statement C. Work breakdown structure D. WBS dictionary
What is A. Scope management plan
100
Validate Scope can be BEST described as the process of A. Validating that the project quality requirements have been met B. Obtaining stakeholder's formal acceptance of the project deliverables C. Controlling changes to the scope of the project D. Validating that all of the project's objectives have been met
What is B. Obtaining stakeholder's formal acceptance of the project deliverables
200
Facilitated workshops are used to gather requirements and should include which of the following stakeholders? A. All Stakeholders B. Project Team C. Cross-functional Stakeholders D. Subject Matter Specialists
What are C. Cross-functional Stakeholders
200
During what part of the project management process is the project scope statement created? A. Initiating B. Planning C. Executing D. Monitoring and controlling
What is B. Planning
200
The scope baseline is comprise of which of the following? A. Scope Statement, WBS, WBS Dictionary B. Scope Baseline, WBS, WBS Dictionary C. Project Management Plan, WBS, WBS Dictionary D. Scope Statement, WBS, Work Packages
What is A. Scope Statement, WBS, WBS Dictionary
200
After delivering a release, the client is adamant that certain features of the software do not provide any business value. Which document can you share with the client to show how the features directly correspond to business needs and requirements stated at the being of the project? a) Requirements Traceability Matrix b) Project Charter c) Scope Statement d) Scope Baseline
What is a) Requirements Traceability Matrix
200
The Delphi Technique involves soliciting feedback from experts in which of the following manner? A. Anonymously B. In a Focus Group setting C. Brainstorming D. Written Correspondence
What is A. Anonymously
300
Organizational Process Assets include which of the following? A. Organizational Culture B. Organizational Structure C. Human Resources D. Organizational Standard Processes
What is D. Organizational Standard Processes
300
If the project is terminated early, the level and extent of completion should be documented. This is done as a part of: A. Define Scope B. Create WBS C. Validate Scope D. Control Scope
What is C. Validate Scope
300
Validated deliverables is an input to which of the following processes? A. Collect Requirements B. Define Scope C. Create WBS D. Validate Scope
What is D. Validate Scope
300
What process group does "Create WBS" belong to? A. Initiating B. Planning C. Executing D. I have no clue
What is B. Planning
300
A new project manager is being mentored by a more experienced certified project management professional ("PMP"). The new project manager is having difficulty finding enough time to manage the project because the product and project scope are being progressively elaborated. The PMP-certified project manager mentions that the basic tools for project management, such as a work breakdown structure, can be used during project executing to assist the project manager. For which of the following can a work breakdown structure be used? A. Communicating with the customer B. Showing calendar dates for each work package C. Showing the functional managers for each team member D. Showing the business need for the project
What is A. Communicating with the customer
400
All of the below are inputs to Define Scope process EXCEPT: A. Project Charter B. Requirements Document C. Organizational process assets D. Project Management Plan
What is D.Project Management Plan
400
Requirements should be gathered from which of the following groups? A. Project Manager B. Project Team C. Project Team, excluding the Project Manager D. All Stakeholders
What are D. All Stakeholders
400
You can determine whether requirements have been met by using ___________ A. Quality Audits B. Inspection C. WBS D. Scope Statement
What is B. Inspection
400
What should be done by the project manager to ensure that all work in the project is included? A. Create a contingency plan B. Create a risk management plan C. Create a WBS D. Create a scope statement
What is C. Create a WBS
400
The Project Scope statement includes which of the following components? A. Project Purpose or Justification B. High Level Risks C. Summary Schedule, Budget D. Project Acceptance Criteria
What is D. Project Acceptance Criteria
500
Which of the following can be BEST described as a characteristic of Work Package? A. May or may not be cost estimated B. Can be scheduled C. Can be further decomposed into work packages D. May be monitored subject to nature of the project
What is B. Can be scheduled
500
A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is: A. Create a project scope statement B. Confirm that all the stakeholders have had input into the scope C. Analyze project risk D. Begin work on a project management plan
What is B. Confirm that all the stakeholders have had input into the scope
500
The preparation of the scope baseline can BEST be described as involving: A. The functional managers B. The project team C. All the stakeholders D. The project expediter
What is B. The project team
500
As a project manager, you should follow which of the following in order to ensure clear boundaries for project completion: A. WBS B. Scope Verification C. Scope Statement D. Scope Control
What is C. Scope Statement
500
Which of the following documents is used as the baseline for evaluating whether requests for changes or additional work are contained within or outside the project's boundaries and guiding the team through the Executing processes? A. Project Charter B. Project Scope Statement C. Project Requirements Documentation D. WBS Dictionary
What is B. Project Scope Statement