Microsoft Project
SSI Tools
Earned Value Management
Misc
Gary Arnold
100

How many baselines does Microsoft Project allow you to save?

11

100

What is our most popular tool?

The Trace Tool (Driving/Critical Path tool)

100

How many EVM guidelines are there?

32

100

What term do we use that means "to clean the schedule out of senitive or non-value added data before we send it to an outside organization"?

Sanitizing the schedule

100

How long has Gary been doing this for?

30 years

200

This condition exists when a successor activity has started or finished before the requirements of its predecessor have been met.

Dependency Out of Sequence

200

What programming language were all SSI Tools originally written in?

Visual Basic for Applications (VBA)
200

What is the main data included in the IPMR format 1?

The BCWS, BCWP, and ACWP of each WBS element

The BAC, ETC, and VAC of each WBS element

The SV and CV of each WBS element.

200

Which customer has the most seats of SSI Tools?

Honeywell
200

What company was Gary working at when he first started being a Project Scheduler?

Motorola

300

What does the "Effort Driven" flag do?

When it's turned on, it keeps the total amount of labor hours on a task constant when new resource assignments are added to the task.

300

What is the official name of the tool that creates status sheets?

Status Turnaround Workbook Tools

300

Who brought Earned Value Management to the Federal Government?

Robert McNamera

300

What is "Driving Slack"?

The amount of slack or float an item has before it begins to drive a focus point.

300

Who was the first contractor Gary hired to work at SSI?

John Senini

400

This table will allow you change a resource's rate over time

Cost Rate Table

400

Name 5 of the tools or features within the "SSI Toolbox"

Add common predecessor

Add common successor

Add common prefix

Add common suffix

Replace text

Trim text

Make text proper case

Slack Evaporator

400

What is the new schedule deliverable called in the IPMDAR?

The Schedule Performance Dataset (SPD)

400

Approximately how many hours of live webinar trainings do we host per month?

10

400

What did Gary do for work before he worked for the company that became a project scheduler with?

Auto mechanic

500

What is the difference between Project Server and Project Online?

Project Server = the server is controlled and maintained on premises of the company who is using it.

Project Online = The server is controlled and maintained by Microsoft (in the cloud).

500

What field is used as the default value for the Trace Log in the Trace Tools?

Text10

500

What is the difference between a WBS Dictionary and WBS Index?

The WBS Index ties a WBS number to one or multiple SOW paragraph reference


The WBS dictionary provides a technical write up of the scope of work that will be performed on the WBS element

500

What was the schedule XML deliverable for the IPMR called

UN/CEFACT XML

500

What was the original company name of Gary gave to SSI?

Change Point Services of America

M
e
n
u