There are Rules
Tie off
Nuts and bolts
100

What is the most cited steel citation

Lack of fall protection

100

Above what height must fall protection be provided to iron workers by the employer and worn by the employee?

15'

100

Rigid frames must have what % of bolts installed prior to disconnecting from the hoist.

50

200

Name 2 exempted steel structures not covered by the steel erection standard.

Electrical towers, communication towers, tanks.

200

Above what height does an iron worker need to tie off?

30'

200

Diagonal bracing must have how many wrench tight bolts installed prior to releasing the hoist 

1

300

What two paperwork items must be given to the steel erector by the controlling contractor

Cure cert, Anchor bolt modification approvals

300

What is the area called where fall protection doesn't need to used between 15' and 30' in the air

Controlled decking zones

300

When installing double connections how many bolts must remain intact while making the second connection.

1

400

Who is responsible for adequate ground access on the site during steel erection

The controlling contractor

400
Perimeter cable used as handrail on building must be in once the ___________ is installed

Decking/Floor

400

When erecting open web or bar joists with lengths over 40' they must be able to be _________ bolted.

Temporary of field

500

What is the maximum number of steel members that can be lifted tied to each other

5

500

What other job other than deckers are not required to use fall protection between 15' and 30'

Connectors

500

A person must be a _________ person to train workers in Christmas treeing, connecting, CDZ procedures

Qualified 