Tecolote's logo includes this animal
What is an owl?
This person's middle name is their parent's middle names
Who is Brittany?
PPBE
What is Planning, Programming, Budgeting, and Execution?
What is a Work Breakdown Structure (WBS)?
This is defined as the longest path through the project
What is the Critical Path?
Tecolote was founded in this year as a two-person company
What is 1973?
This person met actress Jaime Pressly at a Blockbuster
Who is Kimberly?
IMS
What is Integrated Master Schedule?
This cost estimating methodology compares a new system to a similar system where historical cost information is available
What is an analogy?
This is the lowest level of detail within the WBS
What is a Work Package?
This cost estimating software is developed & maintained by Tecolote
What is ACEIT?
This person once spent time in a straightjacket
Who is Brian?
LCCE
What is Life Cycle Cost Estimate?
This document ensures that cost projects are based on a common definition of the system and acquisition program
What is a Cost Analysis Requirements Document (CARD)?
This type of activity must be finished before another activity can start
What is a predecessor activity?
Tecolote's slogan is "Bridging ______ & ______"
What is Engineering & Economics?
This person once met Wiz Khalifa in an elevator
Who is Camilo?
APB
What is Acquisition Program Baseline?
This analysis measures the volatility of cost to changes in input parameters?
What is Sensitivity Analysis?
The necessary delay in the start of a successor activity
What is a lag?
Dahlgren Operations started in this year
What is 2007?
This person provided an extremely long name of a church in Portugal that they visited
Who is Lance?
ACWP
What is Actual Cost of Work Performed?
This secondary methodology is used to validate the reasonableness of estimate results
What is a crosscheck?
The ratio of earned value to planed value
What is the Schedule Performance index (SPi)?