What does LPR stand for?
Labor Production Report
What does CAC stand for in the context of financial forecasts?
Cost at Completion
CBC, stands for this.
Control Budget Change
What is the form that must be submitted to accounting to initiate the creation of a newly awarded project?
Job Setup Form
The BCU Scheduling Department is managed by this man.
Ramzi Pio
What Procore tool is used to document daily jobsite activities and conditions?
Daily Log
Cost at Completion, or CAC is the sum of CTD and this other variable.
CTC or Cost to Complete
All budget moves in a CBC must net to this value.
Zero.
An RM4 is also known as.
Project Kickoff Meeting
A project's activity hierarchy is known as this 3 letter initialism.
Name 1 Safety Cardinal Rule
1. Always Wear your PPE.
2. Do not start work without a job briefing.
3. Keep a clean and organized site.
4. Do not put yourself or others at risk.
5. Follow safety signs and procedures.
6. Never work in unsafe areas.
7. Report all Events and Concerns
8. Never tamper with equipment.
9. Use the right equipment.
10. Proper Lifting Techniques.
11. Safe Vehicle Operation.
12. If in doubt, ask!
This metric is uploaded to COINS from Heavyjob before each month end prior to the period being opened for teams to start their forecast.
QTD, Quantity to Date, or Quantity.
All moves of labor budget dollars should be accompanied by a move of these.
Labor Hours
Prior to mobilization, a COI should be requested from this external entity.
Willis Towers Watson, or WTW.
This type of schedule is typically submitted within 30 days of NTP and serves as the benchmark for the project.
Baseline Schedule or Baseline
Operator Qualifications, or OQs, are run through this organization for NGRID?
National Gas Association, or NGA.
What is the forecasting method of extrapolating unit cost to date?
Straight Lining.
This type of code is permitted to be added with zero budget.
Time and Material
This process is the act of transforming an Estimate into a Control Budget for the project team to execute the job within.
Conformance, Estimate Conformance or Budget Conformance.
Bond Building's VDC group can help create this type of animated schedule, that visually depicts a model of the project being built.
4D Schedule or 4D Simulation
Request this data that specifies trench box load ratings from the G&W when one is delivered to your jobsite.
Tabulated Data or Tabbed Data
The tab within the forecast module that you should use to calculate your CAC is.
Key Fields
CBCs with budget adds or deletions are required when scope has changed and must be approved by a person with this position in the company.
Project Executive
Estimate dollars allocated for risks, either known or unknown, should be budgeted to a cost code of type 9170 and line item'd on this log.
Contingency Release Log or Contingency Release Plan.
XER is a common P6 file format, but it is advised that in most cases, this other 3 letter format be used.
XML