A-D
E-I
J-M
N-R
S-Z
100

BOM

Bill of Materials: A list of sub-assemblies, parts and the quantities of each needed to manufacture an end product.

100

HOGV

Hydraulically Operated Gate Valve

100

MGV

Manual Gate Valve

100

RFQ

Request for Quote: A request that is submitted to a supplier for pricing, delivery and other terms and conditions of purchase.

100

SLT

Senior Leadership Team

200

ASME

American Society of Mechanical Engineers: Boiler and Pressure Vessel Code Sections III and IX

200
EDM

Electric Discharge Machining: Manufacturing process using sparks to acquire the desired shape.

200

MSSRV

Main Steam Safety Relief Valve

200

QMP

Quality Management Procedure

200

VDM

Valve Design Manual

300

CSP

Commercial Spare Parts: Interchangeable part to replace a lost or damaged part of a machine.

300

FWP

Formal Work Procedure: A specifically outlined process of how a task (or set of tasks) is to be performed to ensure consistency.

300

JWP

Joint Weld Procedure: A document that defines how a joint in a weldment is to be performed.

300

NDT

Non-Destructive Testing: A determination of material or a component used for its intended purpose, which does not affect its serviceability.

300

WPS

Welding Procedure Specification: A document providing the required welding variables for a specific application to assure repeatability by properly trained welders.

400

ATV

Astern Throttle Valve: Used in marine steam turbine propulsion plants to prevent steam from leaking into the astern turbine while the vessel is operating in the ahead mode.

400

GFE

Government Furnished Equipment: Equipment that is owned by the government and delivered to, or made available to a contractor. GFE is typically specified in the contract.

400

MTR

Material Transfer Request: Required when Planning desires to utilize an item in lieu of the item released by Engineering for the applicable project.

400

PQR

Procedure Qualification Record: A record of welding variables used to produce an acceptable test weldment and the results of tests conducted on the weldment to qualify a welding procedure specification.

400

VIR

Vendor Information Request: A form to request information or clarification pertaining to a specific discrepancy with a drawing or design.

500

CDD

Contract Delivery Date: Final date the product must be delivered for the terms of the contract to be fulfilled.

500

FAT

Factory Acceptance Testing: A process that evaluates a product during and after the assembly process, verifying it is built and operating in accordance with specifications.

500

MTR

Metallurgical Test Report: A report identifying the results of destructive and non-destructive tests conducted to support evaluation of a Welding Procedure.

500

OEE

Overall Equipment Effectiveness: Takes into account the various sub components of the manufacturing process like availability. After the various factors are taken into account the result is expressed as a percentage.

500

TERI

Technical Evaluation of Replacement Item: An evaluation performed on a replacement item to assure that the correct requirements for an item are specified in a procurement document.

M
e
n
u