Contract Names
Who's That Vendor
TSL Facts
Wild Card
100

LO-2103

CTG


100

LO-2111 Electrical Enclosures

Cape Electric

100

In the TSL arrangement, who primarily handles detailed Balance-of-Plant (BOP) design and engineered equipment procurement—TIC or Sargent & Lundy?

Sargent & Lundy

100

In what state is Richland Parish located? 

Louisiana

200

LO-2130

Heat Tracing

200

LO-2134 Severe Service Ball Valves 

ValvTechnologies LLC 

200

What is the typical unit configuration for TSL’s combined-cycle plants in the Entergy program?

1 × 1 × 1 combined-cycle block

200

What was Traceviews Initial name? 

Madison County

300

LO-2171

Noise Modeling

300

LO-2146 Fire Protection

Continental Fire Sprinkler Company

300

For the Entergy combined-cycle projects, what three agreements collectively govern the relationships among Entergy, Mitsubishi Power, and TSL Power Partners (TIC/S&L)?

EPC Contract/Agreement, TSL Joint Venture Agreement, and Consortium Agreement

300

What does IPG Stand for? 

Integrated Power Group

M