Scope Definition
Scheduling
Cost & Budget
Risk
Planning and JP Development
100

Document listing all the jobs to be executed during the Turnaround.

What is the Scope of Work?

100

Visual document that organizes activities on a timeline

What is the Gantt chart?

100

Estimated expenses required before executing a turnaround

What is the TA Budget?

100

Exercise to evaluate the risk in every TA phase

What is TRM?

100

Documents that establish engineering or technical requirements for products, practices,  methods or operations.

What is a Standard?

200

Review that eliminates non-esencial jobs to optimize time and cost.

What is Scope Challenge?

200

Key source calculated with Duration and manpower

What is man-hours?

200
Materials with cost over 50,000 SAR..

What is a Capital Spare?

200

Document use to record all identified Risk, mitigation plan and contingency Plans

What is the Risk Register?

200

Is the document use by operations to marks the locations of the required Blinds, connections and disconnections..

What is a P&ID?

300

Name of the first tool used in the Scope Challenge

What is Scope Validation Tool?

300

Meeting perform to inform progress of TA to management and to address problems dificult to solve by the PMT

What is Steering Commitee?

300

Service with a cost more than 200,00 SAR

What is the Capital Service?

300

number of TRM perform including all TA phases?

Are they TRM-1, TRM-2, TRM-4 ?

300

Standarize specification that defines the technical requirements for piping componentes in a plant.

What is Piping Class?

400

Tool used to analize jobs using risk and cost

What is Scope Challenge?

400

Scheduling technique that identifies the longest path determining project duration.

What is the Critical Path?

400

Cyclic activities expenses in material and services are consider..

What is TA budget?

400

process of identifying, analyzing, assessing and monitoring the risks of turnaround and take appropriate measures to mitigate identified risks

What is TA risk Management (TRM)?

400

Is the sequence of activities that marks the longer duration in a TA.

What is a Critical Path?

500

It is done just after finalizing the Scope of work and no more activities suppose to be added without addional procedures..

What is the Final Job list?

500

It is the most common software use to schedule activities and control progress of TA

What is Primavera P6?

500

responsible to submit the TA Capex for M-CITT approval

Who is the PMT?

500

Is a Plan performed to minimize the Likelihood of ocurrance of a Risk

What is Mitigation Plan?

500

Document use to define the location of facilities, heavy and mobile equipment in the Plant, MOC signed by Operation and Management

What is the Area Reclasification document?