GAM
Encumbrance
Implementation
Closeout/Payment
Contracting
100

GAM abbreviation meaning

What is Grants Administration Manual?

100

Cost share project funds need to be WCD Board approved/encumbered before this can happen

What is project installation?

100

On-site checks during construction and throughout project lifespan

What are project inspections?

100

Document that certifies submitted cost share project materials are accurate and a true summation of actual costs of practice construction 

What is a project voucher?

100

Two types of cost share contracts most often utilized by WCD

What is percentage based and flat rate?

200

Location of BWSR grant program requirements 

What is the grant agreement (Exhibit A)?

200

Cost share projects need to be internally ranked by this group before WCD Board approval/encumbrance

What is the Cost Share Subcommittee?

200

Document required for each cost share project to ensure successful implementation over the project lifespan

What is an Operation and Maintenance Plan?

200

Minimum number of years that cost share project files need to be kept beyond life expectancy of the installed practice

What is six?

200

Last cost share contract signature line to be signed/dated

What is Authorized Signature/District Manager?

300

Recommended best practices, helpful context, and/or tools/resources/templates to meet the terms of a grant agreement

What is guidance?

300

Minimum number of quotes the WCD requests applicants obtain for cost share projects

What is two?

300

Minimum number of days an applicant has to request an extension to the cost share project install-by date

What is 30 days?

300

The applicant should be sent these four things after WCD Board approves a cost share project payment request

What is payment decision letter, fully signed voucher, copy of as-built, check

300

Applicant's time on project install can be counted as

What is match?

400

Required action to be followed or the steps necessary to meet the terms of a grant agreement

What is procedure?

400

At minimum, the applicant should be sent these items after WCD Board approval/encumbrance of cost share project funds

What is project funding approval letter and fully executed contract?

400

Scheduled time to review final plans, permitting, construction schedule, prevailing wage, etc. with all necessary parties

What is the pre-construction meeting?

400

Grant manager should update these three grant/project platforms at project closeout

What is grant log, eLINK, and WCD BMP database?

400

Four amendment types to an original cost share contract

What is date, amount, land occupier/landowner, practice?

500

Grantees must follow this version of the GAM for their BWSR grant

What is the current version of a GAM chapter, OR older version of GAM chapter as far back as the year of the grant agreement

500

Document that houses local guidelines for the use of grant funds that are specific to WCD 

What is the WCD Cost Share Policy?

500

Party responsible for necessary project repairs if a cost share project fails prior to the minimum practice lifespan

Who is the applicant?

500

Four types of information required on invoices or receipts

What is vendor name, materials, component unit costs, and date work performed?

500

The latest WCD Board meeting to approve a cost share project payment request, when the grant expires Dec 31, 2026 and project work is completed before grant expiration/install-by date.

What is January 2027 Board meeting (before February 1st grant reporting deadline)?

M
e
n
u