100

Task that consist of management or support type activities that have no identifiable end product.

What is a level of effort (LOE) work package?

100

Provides a complete and current definition of the work scope associated with each WBS element to the control account.

What is a WBS dictionary?

100

Longest contiguous sequence of activities to an interim milestone such as design review or phase completion.

What is a Driving Path?

100

The intersection of the WBS and OBS.

What is control Account (CA)?

200

It has a WBS and OBS structure and is also dollarizes.

What is a Responsibility Assignment Matrix (RAM)?

200

It provides the WBS element name and the associated WBS element level and WBS ID.

What is a WBS Index?

200

It identifies all contractor defined fields, definitions, code structures in the IMS, subcontractor activities, risks, SVTs, critical path.

What's an IMS Data Dictionary?

200

At a minimum, work scope, schedule (Control Account period of performance), budget by cost elements, and responsibility (CAM).

What's required in a control account authorization (CAA)?

300

It has a predecessor and successor.

What is horizontal integration in the IMS?

300

It includes work teams, functions, integrated project teams, or other organizational elements responsible for accomplishing project objectives.

What is an Organizational Breakdown Structure (OBS)?

300

Provides the detail necessary for effective execution of the baseline plan, and fully represent the assigned work scope in terms of time phased activities.

What is a work package?

300

PEP, Contract, PO, Inter-agency agreement, and MOU.

What are some different types of customer authorizations?

400

At least annually, projects conduct a comprehensive cost review.

What is a Comprehensive Estimate at Completion (CEAC)?

400

Provides the detail necessary for effective execution of a defined scope within a  control account, fully represents the assigned work scope in terms of time phased resource loaded activities, and serves as vehicle for monitoring and reporting progress and accomplishment of work.

What is a charge number or Project/Task?

400

Zero duration activities that may include: Project start and finish dates, Major events, and Customer reporting.

What is a Milestone?

400

Project (purpose/goal/objectives), SOW, and high level (risks & opportunities).

What's in a project charter?

500

A logical aggregation of work within a control account, normally the far-term effort, that can be identified and budgeted in early baseline planning but cannot yet be defined into work packages.

What is a planning package?

500

The integration between the project's WBS OBS, CA, WP, PP, and summary level planning package ID, and charge numbers.

What is a Data Item Matrix?

500

It helps determine that the schedule is reasonable as a baseline for achieving project objectives.

What is a Schedule Health Assessment?

500

Authorizes all control account work scope including associated work packages.

What is a Control Account Authorization (CAA)?