Phone number extension to the WL security office?
ext. 7259
How long is a project barricade tag normally good for?
7 days
What is the name of the computer software we track near misses and incidents?
Gensuite
What type of physical hazard does Chlorine create
Inhalation hazard
Name the two areas of the WL Plant where hi-visibility clothing must be worn
Warehouse & Backyard
What distance (in miles) of lightning requires us to secure all crane and lift activity and bring everyone indoors?
10 Miles
What 2 forms should we use for weekly and daily project planning?
Daily safety checklist / Job Plan
MOC is not required when temporary changes are only for a short period of time time
True or False
False
At what height should you be tied off for fall protection?
4ft from a leading edge
How often should a fire extinguisher be inspected?
Every 30 Days
What OSHA training is required for construction contractors?
OSHA 10-hour
The phrase “Corning First, Corning Last” is associated with what specific work permit?
Lockout Tag out permit
Tinted safety glasses are allowed when working in the warehouse area
True or False
False
How many pounds should your anchor point be able to hold for fall protection?
5000Lbs.
how often hard hats should be replaced?
Every 5 years from the date of manufacture
Who is ultimately responsible for your personal safety out here on the projects?
YOU are responsible for your own safety
Not Juan, John or Bob!!!!
Main purpose of the NFPA 70E standard
Provides guidelines to protect workers from major electrical hazards
These barricades do not restrict personnel access, and Barricade Tags are not required
Yellow barricade
What protection is required for all extension cords?
GFCI - Ground Fault Circuit Interrupter
“Hot Work Permit” for welding/grinding/etc. requires clearing of all combustibles within how many feet?
35-foot radius
An unplanned event that did not result in injury, illness, or damage but had the potential to do so.
Near Miss
What is the OSHA Threshold Quantity for Chlorine?
Threshold quantity (TQ) for chlorine gas is 1,500 pounds
What does MCS and MCN stand for?
MCS - Management of Change System
MCN - Minor Change Notification
What is the first thing you should do during a plant evacuation after you have safely exited the building
Badge in at one of the Mustering Stations
All safety glasses worn on site must meet which standard?
ANSI Z87.1