The Facility Number for drawing number 1475-C-001 (Scenic East Pumping Plant) is???

A: Other

B: 001

C: 1475

A: Other (343)

Per ESP 120.6: 1475 is the structure number . To find the Facility Number for Structure Number 1475, you the Facility Guide to look it up.

100

Drawing Number 3000-A-001.00


What is the Serial Number?

001

Per ESP 120.6

100

Walnut Creek Filter Building: What is it's substructure number?

20

150

Where is the fastest place to look up a the structure number for existing facilities? 

Facility Guide. Bonus question: What other information can you find in the Facility Guide? 

150

What is an equipment tag?

Per ESP 130.0: Uniform means of identifying individual pieces of equipment at District facilities.

150

Who assigns structure numbers? 

Allen Gerten in Engineering Records per ESP 120.4

175

In a Water Facility, what are components of an equipment tag?

Per ESP 130.0

Facility Number - System - Equipment Code- ID Number - Modifier (Optional)

175

Where is the best place to get a list of all the substructure numbers?

Allen Gerten. Per ESP 120.6, this list is maintained by Engineering Records.

175

Who assigns Facilities Numbers? 

Mark Foley in Asset Management per ESP 130.0

200

What type of facilities have substructure numbers?

Water Treatment Plants and Water Supply Reservoirs

200

The medium voltage switch gear located at Maloney PP (Facility # 314) feeds Sobrante WTP (Facility #236). The facility number for the medium voltage switchear wil be Maloney PP or Sobrante WTP? Why?

This exact example is from ESP 130.0. 

The facility number for the medium voltage switchgear will be 236 because Sobrante WTP is the major facility. 

200

If you are looking for an O&M manual in DOCS, can you use the equipment tag to quickly look up an O&M?

Yes, but it all depends if the person uploading inputs that information into DOCS 

250

True or False:

Per ESP 120.4, a co-located pumping plant and reservoir, a drawing will take the structure number of the pumping plant unless the drawing pertains to the reservoir only. 

True. 

250

Can you rev-up a Z drawing for your new project?

No. Per ESP 120.6, new projects have the  next serial number in a sequence. 

The next project will have Z-002, and the project after that will have will have Z-003

250

MCC is feeding two pumping plants: Maloney (Facility #314) and Greenridge (Facility #298). What will the facility number be for the MCC and Why?

Per ESP 130.0