Policy Review:
MOC
Right now
PEM
Pot Luck
100

when do you need to fill out IOGPs / Start work checks  

before starting work

100

The type of thread on the DP & HWDP.

Delta 391

100

yesterdays drill was?

natural gas

100

The size of 272's drill line

1 3/8" diameter

200

When would a Subject Matter Expert be used help review or plan a JMR?

Subject Matter Experts (SME) may be chosen to give input and help the Senior Technical Manager (STM) make decision, but are not mandatory.

200

according to Patterson's wind chill chart what needs to be done in the GREY ZONE ?

Take regular, sufficient breaks every 30 minutes in warming areas. Wind chill is monitored each hour and documented.

200

Today's Patterson UTI Core Value


safety and environment 

200

Name the BOP stack components in order, top to bottom

Annular, blinds, upper rams, mud cross, lower rams

300

Using the Jobsite Modification Matrix, determine the JMR Category and Approver for a modification that would cost an estimated $50,000.

Cat: 3 - Major

Approver: VP Technical Services

300

what must be in place for a vehicle 1 ton or greater?

wheel chocks 

300

what is Chevron's tenet of the day?

9.Follow written procedures for high risk or unusual situations

300

The Rated Pressure/Maximum Allowable Working Pressure (MAWP) and the Working Pressure of the annular are:

Rated Pressure/Maximum Allowable Working Pressure (MAWP) is 5000 psi (initially tested to 5000, subsequently test to 3500 psi).  The Working Pressure range is 700-1500 psi (depending on tubular size).



400

What are the different types of respiratory protection available at Patterson-UTI worksites?

n-95 respirator, air- purifying respirator, self-contained breathing apparatus, rescue pack.

400

These are the rig's pneumatic system & hydraulic system pressures

Pneumatic: 120 psi, Hydraulic 2800-3000 psi

400

When Bringing pumps up to speed ( BPUTS) what Pressure do you hold constant?

C)   shut in casing pressure (SICP)

400

This city is known as the energy capital of the world

Houston, TX

(Tulsa, OK is known as the oil capital of the world)

500

what start work check (IOGP) should be reviewed & filled out, prior to using the hook under the boom of the fork lift?

Mechanical lifting

500

what type of cord does a power tool need to be used on location?

three-wire grounding cord or be marked as double insulated.

500

Why do you use a diverter?

to direct fluids away from rig floor.

500

TFA means...

Total Flow Area

(the total amount of fluid flowing through the nozzles)