Project Package Review
Pre-Implementation Actions
Pre-Implementation Site Survey
Project Implementation
Post Implementation-Actions
100

The form number for the Project package review

What is AFTO Form 750/750A?

100

The form number for the, Engineering Installation Pre/Post Implementation Checklist.

What is "AFTO Form 751"?

100

Form used to confirm the availability of all project materiel, ensure proper completion of allied support, the status of support facilities, and to evaluate whether a project can begin. 

What is AFTO Form 753, Pre-Implementation Site Survey (PSS) Checklist

100

If deficiencies are encountered which cannot be resolved during testing, contact the ____________ for guidance. Also, advise the customer QA section

What is "project engineer and PM "?

100

The ____________ is used for the official customer acceptance and closeout process.

What is "AFTO Form 747 Cyberspace Infrastructure Systems Acceptance Certification "?

200

The LOM consists of two sections. This section lists end items of equipment required for the project, real property, and items to be provided by the customer.

What is "Section 1"?

200

This person initiates the Engineering Installation Pre/Post Implementation Checklist.

Who is "the Team Chief's supervisor, or applicable full-time representative"?

200

Upon completion of the materiel inventory of the LOM, if the project is in jeopardy or if a delay is anticipated due to lack of materiel, the Team Chief should draft a _________________.

What is a Materiel Discrepancy email?

200

Complete and process an __________ through the local base fire department prior to beginning any torch work, brazing or working on lead, or exothermic welding.

What is "AF Form 592"?

200

As a close out action the Team Chief should provide an __________ and check with host base POC to assist in disposition instructions for left over materiel

What is "excess/residue LOM"? 

300

While ensuring all drawings listed on the PSA drawing list are also listed on the project Drawing List and are on hand. Each drawing be checked for for the following.....

What is "Drawing Numbers, Sheet Numbers, and revisions"?

300

During the pre-implementation process the work center POC initiates an AFTO Form _____ for each project. This is a permanent record of all project actions to include; tasks completion, problem areas, team complement, site visits, in and out briefs, project POCs and vehicles. 

State the form number and its official title.

What  is AFTO Form 752, Engineering Installation Project Report?

300

If during the PSS it is determined that the project cannot proceed on schedule, _____________?

What is "notify the EI unit PM immediately"?

300

Before working aloft, ensure a site specific ________ is in place IAW AFI 91-203

What is "rescue plan"?

300

As a close out action the team chief will ensure all applicable actions identified in section C and D of the ___________  are complete.

(Form Name) 

What is "AFTO Form 751 Engineering Installation Pre/Post Implementation Checklist. ?"  

400

This is the proper recourse  if the Team Chief and the Engineer Disagree on a change to the Project Package.

What is "the PM sends the package to the unit Quality Assurance for final resolution?"

400

This form is a daily log and is used by the team chief to record, on a daily basis, all events impacting the project to include: All safety briefings, leaves, job progress, problems encountered (even though the problem may have been resolved), changes in personnel, vehicle status, resolution of previously identified problems, site visitors, materiel issues, support issues, and any other pertinent information.

What is "AFTO Form 752A, Engineering Installation Project Report Daily Log, Continuation"?

400

_____________(end items of equipment controlled via CA/CRL) remain the property of the using command and at no time will team chief accept accountability for them.

What is "Command assets"?

400

Accurate project status reporting to the home unit and the customer is extremely important. Frequency of team chief reporting varies according to job complexity and installation, support, and personnel problems encountered. The AFTO Form 752, Engineering Installation Project Report will be used to track job status. A project status update will be provided to the EI unit PM  __________ at a minimum.

What is "weekly"?

400

If an out-brief is declined, note this in the __________.

What is "AFTO Form 752 Installation Project Report Daily Log, Continuation."

500

The  systematic four-step process of a  project package review. 

What is Inventory, Familiarization, Review, and Documentation?

500

The proper format of the Subject line in a Team Chief's official Email.

What is "Project#, Short Title of Job, and (Subject & Date)."

Example: 

QJKD-2021-000001, Fiber Install, (Notice of Arrival, 16 Jun 2021)

500

______________ should include complete information regarding wrong item sent, incorrect quantities, poor storage facilities, and actions taken to correct the discrepancy. Attach a LOM indicating these items. Always indicate the projected date materiel shortage will impact the project.  

What is " The Material Discrepancy Email"? 

500

The drawing shall be updated using the following color code.

_________Deleted items from drawings 

_________New additions to the drawings 

_________-Instructions/notes to the engineer or drafter 

What is....? 

YELLOW    Deleted items from drawings 

RED          New additions to the drawings 

BLUE        Instructions/notes to the engineer or drafter.

500

During the outbrief  the Team Chief should inform customer to expect to receive an automated ______________.

What is "AFTO Form 761, Customer Satisfaction Questionnaire (CSQ)."?