Cut resistant gloves with a Minimum ANSI/ISEA Level ______ are required on the job at all times.
Level 2
A- frame step ladders over ___ feet in height shall be of the platform or podium type and must be equipped with cross member that lock rigidly in place.
4 feet
All tower cranes, construction personnel or material hoists and/or other crane set up or assembly on the project will require ____ inspection.
Third party inspection
Where is the muster point for EOB Wynn?
Employee Parking Lot
Anchorages used for attachment of personal fall arrest equipment shall be capable of supporting at least ______ pounds per employee attached.
5,000 Lbs
Does a government employee/ Osha representative required to where PPE on job sites?
Yes in required areas
At what size doses a hole need to be protected?
2 in or greater
All tower cranes must utilize reliable ____ communications at ground loading zones as well as any designated landing zones.
Two-Way Communication
At what distance doses each fire extinguisher need to be separated?
75 feet
All Trade Partners are required to complete a ______________ before any work is undertaken.
Pre-Task-Plan (PTP)
When drilling overhead, using a chop saw, using masonry/carpenter saw, concrete cutting, grinding, or similar activity what PPE is required?
Face Shield or Goggles
How many perimeter cables are required for perimeter protection?
4 perimeter cables
- A cable at 0 above the deck
- A mid-cable at height of typical middle guard rail
- A cable as a top rail at 39" to 45" above the deck
- A cable 60" above the deck
Any crane load meeting or exceeding 75% of the chart (rated) capacity of the crane, involving multiple crane or hand off picks will require _______.
Critical Lift Plan
After completion of hot work how long doses the fire watch need to be present for?
60 min
Materials shall be stored for no more than _____ duration to minimize storage area issues, unless previously approved by suffolk project staff.
2 Weeks
In windy condition and when working at elevated location, what is required?
Hard hats shall be tethered to the worker to prevent them from falling.
When "Christmas treeing" steel beams, no more than ____ pieces shall be allowed in a single lift and only approved multiple lift rigging shall be used.
3 Pieces
All tower, crawler cranes and on site assembled crane set-ups shall be reviewed by __________ and ________ documentation shall be submitted to the company prior to the equipment being set up in the designated area.
Professional engineer and stamped/sealed documentation
What doses FPPM stand for?
Fire Prevention Program Manager
No one worker is required or allowed to lift or carry more than _________ pounds.
80 Lbs
What PPE is required at minimum at all times for all employees while on the project site?
Approved hard hat, safety glasses, task specific gloves, work boots, long pants, high visibility vest or shirts and short sleeves are required at minimum at all times on the project site.
Where no other fall protection is provided, workers shall wear a properly fitted and adjusted personal fall arrest harness secured to an approved anchorage point when working within six feet of any leading edge or within ___ feet of any unprotected perimeter edge at an elevation of six feet or more from the next lower level.
15 feet
What pieces of information are required for a trade partner to submit in advance for crane activities? (6 elements of the pick plan)
Crane Inspection Records, lift Plan, Operator License, Hoisting License, Medical Examination Card, Pre Task Plan
What size fire extinguisher doses someone need when performing hot work?
20lb ABC fire extinguisher
What is the color code for extension cord inspections this month?
Green