Starting after offload and going till the start of core reload this is critical path
What is the Thermal shield support block bolt remediation and core barrel exams?
The 480V transformer we are replacing
What is the 1-9P Transformer?
(going to be replaced in the front end of the outage and needs to be complete prior to train swap)
Current number of DID windows.
what is 6?
(potentially 5 if we perform well with RW backflow and have RW back before we load the core)
The major vessel component we are pulling this outage
What is the core barrel?
Where we log work stoppage in an outage
What is the Outage directors logs?
Prior to offload and after reload 24 hours of critical path impact is for latching and moving operations in support of this off normal inspection of a in vessel element.
What are guide card exams?
The reason for the dual train river water outage
What are pin hole leaks?
(there is one area of wall thinning and 2 leaks driving pipe replacement in both trains)
Update to DID for when we enter yellow risk for decay heat in the RCS
What is when we are below Pressurizer level?
The type of head inspection occurring this outage
What are top of head inspections?
Where owners reps are populated
What is in one note under directors logs>Project Owner?
Current schedule duration (In days)
what is 31 days?
(assuming one TSSBB repair)
A test on the front end of the outage to design condenser supports to be installed in 1R30
What is the turbine shaker test?
When we start monitoring spent fuel pool as a DID function.
What is when the first fuel assembly is offloaded from the vessel into the spent fuel pool?
The number of TSSBBs there are.
What is 12?
(2 in each location there are also 6 dowl pins)
What we are briefing out at noon/midnight in OCC
What are Field engagement reports as required by the oversight plan?
The duration of outage reduction if bolt repairs are not required.
What is 3 days and 3 hours.
(critical path will still run through refueling and core barrel exams)
The work in the containment in the river water sequence that occurs with 2 cleanings and 1 eddy current on the front end and 2 cleanings and 1 eddy current on the back end.
What is the recirc spray heat exchanger work?
The shortest time to boil
What is 18.3 minutes?
Why we are pulling the core barrel
What is we need to inspect for core barrel cracking to justify continued operation with suspected degraded flextures?
To be completed as soon as practical and emailed out to the management team after an event takes place and notifications are made to the control room and OCC.
What is a PROMPT INVESTIGATION FORM?
The methodology for determining the status of the TSSBB.
What is borescope data feeding a decision tree?
(We have approximately 1/4 inch clearance to pull the core barrel)
The sequence of river water work
What is the B recirc spray HX work, B header for valve work and to fix pin hole leaks, train swap, back flow line up to perform valve and expansion joint work and fix pin hole leaks on the A train, A recirc spray work?
The visual verification we will preform not in the cavity to exit the drain down window
What is that flux thimbles are not leaking at the seal table?
(When we pull flux thimbles up out of the bottom of the core we install low pressure seals that hold back cavity level. we are pulling flux thimbles to the second window again this outage.)
The component we are inspecting with the core barrel pulled to ensure we can reinsert the core barrel
What are Clevis Inserts looking for Separation?
(this is based on OE The clevis inserts are located at the bottom of the vessel they are bolted on and function as guide tabs- it’s where the keyed core barrel interfaces with the vessel.)
New INPO guidance that outlines a set of behaviors to create an environment for seeing, managing and sustaining the highest levels of competence throughout organizations
What is the proficiency model?
(INPO 24-001 Proficiency – Advancing Human and Organizational Performance)