100

Why an estimate cost?

Estimate costs and determining a budget

100

Bottom up estimating

Used to create a total project estimate

100

Control costs

By analyzing and managing costs

100

Planned value

The value of work that should have been completed at specific point of time

100

What is budgeting

Allow or provide a particular amount of money in a budget.

200

Why is project scope Important?

it clarifies what will be done, and usually any limitations, dependencies and assumptions

200

Three point estimating

Looks at the best case, worse case then estimates are made

200

Earned value Management

Used to measure project effectiveness

200

Actual cost

The cost of work that has been completed

200

Cost performance baseline

Authorized time-phased budget used to measure, monitor, and control overall cost performance on the project.

300

Expert judgment

Used to analyze the information needed to develop the scope

300

Activity Cost estimate

 the quantitative process of assessing the possible costs

300

Forecasting

Estimate of future projects performance

300

Earned value

Progress of a project and basis for cost analysis

300

Cost management plan

Document which will outline the criteria and activities

400

Analogous estimating

A high level estimate

400

Basis of estimates

analyzed and carefully calculated number that can be used for proposals, bidding on government contracts, and executing a project with a fully calculated budget.

400

Schedule and cost analysis

Compares amount of work done to time/cost of work to be done

400

Schedule performance index

Amount of work done at a single point of time

400

What will be the Control performance total

CPI=39/50

under budget/on track/over budget

50/39= 1.3

Under budget

500

Parametric estimating

Estimate of the quantity of the work and productivity

500

Why is estimating cost Important?

 it help make the right commitment of dollars to a business activity.

500

Budget at completion

The amount you expect the project to cost

500

Performing cost analysis

Amount of work completed versus what was paid for work to get done

500

What is the Schedule Performance Index (SPI)?

SV=450/525

Ahead of schedule/on track/behind schedule?

SV=EV/PV

1.2 

Ahead of schedule