11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
100

Describes the general approach to managing risk on a project

What is:

Risk Strategy

100

Identify Risks Outputs

What is:

  • Risk Register
  • Risk report
  • Project documents updates
    • Assumption log
    • Issue log
    • Lessons learned register
100

Perform Qualitative Risk Analysis Outputs

What is:

Project documents updates

  • Assumption log
  • Issue log
  • Risk register
  • Risk report
100

Risk Report

What is:

Describes sources of overall project risk and the current overall project risk status

100

Technique that can be used to select a risk response strategy

What is: 

Decision Making

200

Plan Risk Management Outputs

What is:

Risk Management Plan

200

Technique examining the degree to which organizational strengths may offset threats and determines if weaknesses may hinder opportunities

What is:

SWOT Analysis

200

Perform Qualitative Risk Analysis Inputs

What is:

  • Project management plan
    • Risk management plan
  • Project documents
    • Assumption log
    • Risk register
    • Stakeholder register
  • Enterprise environmental factors
  • Organizational process assets
200

Perform Quantitative Risk Analysis Outputs

What is: 

Project documents updates

  • Risk report
200

Plan Risk Response Inputs

What is:

  • Project management plan
    • Resource management plan
    • Risk management plan
    • Cost baseline
  • Project documents
    • Lessons learned register
    • Project schedule
    • Project team assignments
    • Resource calendars
    • Risk register
    • Risk report
    • Stakeholder register
  • Enterprise environmental factors
  • Organizational process assets
300

4 types of Level 1 risks of a Risk Breakdown Structure

What is: 

1. Technical Risk

2. Management Risk

3. Commercial Risk

4. External Risk

300

Risk register content

What is: 

1. list of identified risks

2. potential risk owners

3. list of potential risk responses

300

Considers the likelihood that a specific risk will occur, potential effect on one or more project objectives such as: Schedule, Cost, Quality and Performance

What is:

Risk Probability and Impact Assessment

300

Perform Quantitative Risk Analysis Tools and Techniques

What is:

  • Expert judgment
  • Data gathering
    • Interviews
  • Interpersonal and team skills
    • Facilitation
  • Representations of uncertainty
  • Data analysis
    • Simulation
    • Sensitivity analysis
    • Decision tree analysis
    • Influence diagrams
300

Plan Risk Response Outputs

What is: 

  • Change requests
  • Project management plan updates
    • Schedule management plan
    • Cost management plan
    • Quality management plan
    • Resource management plan
    • Procurement management plan
    • Scope baseline
    • Schedule baseline
    • Cost baseline
  • Project documents updates
    • Assumption log
    • Cost forecasts
    • Lessons learned register
    • Project schedule
    • Project team assignments
    • Risk register
    • Risk report
400

Plan Risk Management Inputs

What is:

  • Project charter
  • Project management plan
    • All components
  • Project documents
    • Stakeholder register
  • Enterprise environmental factors
  • Organizational process assets
400

Identify Risks Tools and Techniques

What is:

  • Expert judgment
  • Data gathering
    • Brainstorming
    • Checklists
    • Interviews
  • Data analysis
    • Root cause analysis
    • Assumption and constraint analysis
    • SWOT analysis
    • Document analysis
  • Interpersonal and team skills
    • Facilitation
  • Prompt lists
  • Meetings
400

Common characteristics of Risk

What is: 

1. Urgency

2. Proximity

3. Dormancy

4. Managemeability

5. Controllability

6. Detectability

7. Connectivity

8. Strategic Impact

9. Propinquity

400

Perform Quantitative Risk Analysis Inputs

What is:

  • Project management plan
    • Risk management plan
    • Scope baseline
    • Schedule baseline
    • Cost baseline
  • Project documents
    • Assumption log
    • Basis of estimates
    • Cost estimates
    • Cost forecasts
    • Duration estimates
    • Milestone list
    • Resource requirements
    • Risk register
    • Risk report
    • Schedule forecasts
  • Enterprise environmental factors
  • Organizational process assets
400

Plan Risk Response Tools and Techniques

What is:

  • Expert judgment
  • Data gathering
    • Interviews
  • Interpersonal and team skills
    • Facilitation
  • Strategies for threats
  • Strategies for opportunities
  • Contingent response strategies
  • Strategies for overall project risk
  • Data analysis
    • Alternatives analysis
    • Cost-benefit analysis
  • Decision making
    • Multicriteria decision analysis
500

Plan Risk Management Tools and Techniques

What is

  • Expert judgment
  • Data analysis
    • Stakeholder analysis
  • Meetings
500

Identify Risk Inputs

What is: 

  • Project management plan
    • Requirements management plan
    • Schedule management plan
    • Cost management plan
    • Quality management plan
    • Resource management plan
    • Risk management plan
    • Scope baseline
    • Schedule baseline
    • Cost baseline
  • Project documents
    • Assumption log
    • Cost estimates
    • Duration estimates
    • Issue log
    • Lessons learned register
    • Requirements documentation
    • Resource requirements
    • Stakeholder register
  • Agreements
  • Procurement documentation
  • Enterprise environmental factors
  • Organizational process assets
500

Perform Qualitative Risk Analysis Tools and Techniques

What is: 

  • Expert judgment
  • Data gathering
    • Interviews
  • Data analysis
    • Risk data quality assessment
    • Risk probability and impact assessment
    • Assessment of other risk parameters
  • Interpersonal and team skills
    • Facilitation
  • Risk categorization
  • Data representation
    • Probability and impact matrix
    • Hierarchical charts
  • Meetings
500

Simulations are typically performed using this analysis.

What is:

Monte Carlo

500

5 alternative strategies may be considered for dealing with threats

What is:

1. Escalate

2. Avoid

3. Transfer

4. Mitigate

5. Accept