COHE
ELECTRICAL SAFETY
BLUE STAKE
GUARDING AGAISNT ENTANGLEMENT
NFPA 70E (ARC FLASH)
100
Potential Fatal Risk associated with COHE

What is Uncontrolled release of energy?

100

Potential Fatal Risk for Electricians

What is Exposure to Electrical Hazards?

100

IF the penetration is (_____) inches or less a blue stake permit is NOT required

What is 1''?

100

There are 3 Primary types of guarding

What are?

Point-of-Contact guarding

Location guarding

Area guarding

100

NFPA stands for

What is National Fire Protection Association?

200

Required when working on equipment for commissioning, testing, calibrating, troubleshooting, etc

What is Energized work permit?
200

Name three critical controls for Electrical Safety

What are?

Access Control

Barriers and Segregation

Electrical PPE

Energized Electrical Work Permit

LOTOTO

Engineering Controls

200

An engineer, technician, or other qualified individual that has the ability to review drawings or prints and mark out utilities and pipelines accordingly

Who is a Blue Stake Representative?

200

Guarding by location requires a distance of at least ____ft

What is 7ft?
200

This individual, in coordination with site leader, is responsible for verifying and documenting that each site is in compliance with FCX-HSO3, the Electrical Safety Policy

Who is the Electrical Safety Lead?

300

Needed when an individual forgets their lock and leaves property

What is Non-Routine Lock Removal?
300

Never assume an electrical circuit is this

What is de-energized?

300

Hand digging/Pot-Holing will be done when working within (_____) inches of known utilities

What is 24 inches?

300

Barriers that prevent entry of a miner into an area containing moving machine parts

What is area guarding?

300

This individual is a qualified Electrical Engineer, competent in performing all analysis required to complete the Arc Flash Study and deliver Arc Flash labels

Who is Arc Flash Engineer?

400

Individual who locks and tags isolation devices for equipment to perform service of maintenance

Who is an Authorized Individual?

400

Two people who must complete and sign Energized Work Permit

Who are the qualified individual doing the work and a member of Electrical Supervision?

400

RED markings for underground utilities indicate

What is Electrical Power?
400

3 examples of acceptable guarding fasteners 

What are?

Bolts

Clamps

Cotter Pins

Wire ties

400

Three phase electrical equipment rated greater than _____V shall have an Arc Flash analysis

What is 240V?

500

Name 5  of the Critical Controls used in COHE

What are?

 Blocking for Maintenance Work

Guards, Barriers, Barricades

LOTOTO

Pipe Management

Hose Coupling Locking Systems

Pipe/Hose/Equip Mechanical Integrity

Relief Valves

Tensioned Lines Management

Tire Management


500

Electrical Gear (breakers, cabinets, switches, panels, etc.) must be labeled to indicate 3 things. Name 2. 

What are voltage, equipment being powered, Arc flash requirements?

500

_________ into floors requires a permit at all times.

What is sawing?
500

Name 3 materials that are acceptable for use in guarding machinery

What are?

Metal

Plastic/Plexiglass

Wood

500

What 3 things must be listed on an arc flash label applied directly to corresponding equipment

What are?

Nominal equipment voltage

Arc Flash Boundary

Minimum required arc rating of clothing