3.03
3.04
4.01
4.02
4.03
100

What is WBS (Work Breakdown Structure)?

The work to be executed by the project team to accomplish project objectives and create the required deliverables.

100

The two aspects of Verifying Scope

Inspection 

Accepted Deliverables

100

What is a Precedence Diagramming Method (PDM)

A graphical tool used for scheduling activities in a project plan.

100

Bottom-Up Estimating

A method of estimating project duration
or cost by aggregating the estimates of
the lower-level components of the Work
Breakdown Structure (WBS)

100

Schedule Network
Analysis

A Schedule Network Analysis is a
graphical representation of a schedule
showing each sequenced activity and the
time it takes to finish each one. It's used
to identify early and late start dates, as
well as early and late finish dates, for the
uncompleted portions of project
schedule activities.

200

What is WBS Dictionary?

Document generated by the Create WBS process that supports the WBS. The WBS Dictionary provides more detailed descriptions of the components in the WBS.

200

The two aspects of Control Scope?

Variance Analysis 

Work Performance Measurements

200

What is Finish-to-start 

The logical relationship where initiation of work of the successor activity depends upon the completion of work of the predecessor activity.


200

Analogous Estimating

The analogous estimating technique
uses information from similar projects to
establish a cost estimate based on the
data available

200

Precedence Diagram
Method

The precedence diagram method (PDM) is a
tool for scheduling activities in a project plan. It
is a method of constructing a project schedule
network diagram that uses boxes, referred to as
nodes, to represent activities and connects them
with arrows that show the dependencies.

300

What is Scope baseline?


  1. The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, a component of the project management plan. Components of the scope baseline include Project Scope Statement, WBS and WBS Dictionary.
300

You are a new project manager that is replacing a previous project manager. You want to know more about the scope baseline of the project. Which three documents will be most useful to you?


Project scope statement, WBS, WBS Dictionary

300

What is Finish-to-finish?

The logical relationship where completion of work of the successor activity cannot finish until the completion of work of the predecessor activity.

300

Parametric Estimating

Parametric estimating is a method to
estimate cost, duration and effort on a
project. It uses a set of algorithms,
statistics or models to describe the
project and is one of four primary
methods that project managers use when
estimating a project

300

Critical Path Method

The critical path method (CPM) is a
technique where you identify tasks that
are necessary for project completion and
determine scheduling flexibilities. A
critical path in project management is
the longest sequence of activities that
must be finished on time in order for the
entire project to be complete.

400

What is Decomposition?

  1. Is the subdivision of project deliverables into small, more manageable components until the work and deliverables are defined to the work package level. The work package level is the lowest level in the WBS, and is the point at which the cost and activity durations for the work can be reliably estimated and managed. The level of detail for work packages will vary with the size and complexity of the project.

 

400

What tool or technique would a project manager use to control scope?

Variance analysis

400

What is Start-to-start?

The logical relationship where initiation of the work of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity.


400

Three-point estimates

Three-point estimating is a management
technique to determine the probable
outcomes of future events based on
available information

400

Critical Chain Method

Critical Chain Method. The Critical
Chain Method (CCM) is used to
perform Schedule Network Analysis that
considers task dependencies, limited
resource availability, and buffers. It's
used to prepare the project schedule
when limited or restricted resources are
available.

500

Which movie did we watch in 3.03?

Oceans Eleven

500

Which of the following individuals in most crucial in validating scope?

Project sponsor or customer

500

What is Start-to-finish?

The logical relationship where completion of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity.

500

Reserve Analysis

The PMBOK defines reserve analysis as
"an analytical technique to determine the
essential features and relationships of
components in the project management
plan to establish a reserve for the
schedule duration, budget, estimated
cost, or funds for a project

500

Resource Leveling

Resource leveling is a resource
management technique that can help
teams better accommodate resource
constraints and predict project timelines.
It helps avoid poor project planning that
often leads to last-minute delays,
overworked team members, and cost
overruns.