Acronyms
Building a Foundation
Structures
Where to Find the Answer
100

EVMS

What is the Earned Value Management System?

100

The number of guidelines that Programs with the EVMS requirement need to be compliant to.

What are 32?

100

The key management control point that CAMs manage scope, schedule, and budget.

What is the Control Account?

100

Corporate manual that provides guidance on how Northrop Grumman applies Earned Value Management.

What is the Northrop Grumman Earned Value Management System Description (EVM SD) (CTM F300)?

200

WP

What is the Work Package?

200

The number of categories that the guidelines are bucketed into.

What are five?

200

The detailed tasks required to accomplish/complete the CA scope.

What is the Work Package?

200

Sector procedure that outlines the various internal EVM reporting requirements by level.

What is Earned Value Management  (F105 SPO)?

300

WBS

What is the Work Breakdown Structure?

300

The budgeted value of the work accomplished.

What is the Budgeted Cost of Work Performed (BCWP)/Earned Value (EV)?

300

This is used when all scope for a control account may not be feasible to detail plan.

What is a Planning Package?

300

Sector template for a Program to detail out their EVM implementation.

What is Space Systems Earned Value Management Plan and Waiver (EV Plan) (SP F105)?

400

OBS

What is the Organizational Breakdown Structure?

400

The documentation that lays out the expectations and reporting of contractor performance data.

What is the Contractor Data Item Description (DID)?

400

Representation of Program Management organizational hierarchy including major subcontractors and inter-organizational efforts.

What is the Organizational Breakdown Structure (OBS)?

400

Northrop Grumman central repository that houses all Corporate and Sector manuals and procedures.

What is Principles and Operating Practices (PrOP)?