Shorings
Soil Types & Sloping
Ladders & Barriers
Utility Safety
Safety Roulette
100

A protective system must be in place at this depth before workers are permitted to enter the trench.

1.2 m / 3.93 ft

100

Soil that is very stiff and dense, has medium internal strength, appears damp after excavation, and can be penetrated with moderate difficulty is classified as what soil type?

Type 2 soil

100

Where must ladders be positioned in relation to the excavation support system?

Within the protected area

100

These people onsite must review locates and confirm it matches marks on ground

Who is EVERYONE? (Crew, hydrovac operator, mechanical operator, Supervisor)

100

The minimum distance any tools, debris, material, or dirt piles must be placed away from an excavation edge.

What is 1 meter?

200

As a trench gets deeper, what must be done with trench boxes to keep workers protected?

They must be stacked on top of each other

200

Soil that shows surface cracking, water seepage, may cave in to a natural 45° slope when dry, or slab off when wet, is classified as what soil type?

Type 3 soil

200

This is the maximum distance a ladder can be from any worker in a trench to ensure safe egress.

7.5 m / 24.6 ft

200

These are the excavation methods you must use when digging within 1.2m of underground utilities.  

hydrovac and hand digging

200

These two activities must never be performed while a worker is inside a trench, as they can lead to sudden collapse, engulfment, or struckby.

Adjusting/installing/removing shoring, and backfilling.

300

Protective systems for excavations deeper than what depth must be designed and approved by a professional engineer? 

More than 6 m / 20 ft

300

Soil that has almost no internal strength, especially when wet or muddy, and is sensitive to vibration, is classified as what soil type?

Type 4 soil 

300

This is how far a ladder must extend above the landing area in an excavation to ensure safe access and exit.

900 millimetres / 35 inches / 3 ft

300

This is the minimum distance you must maintain from an UNEXPOSED utility when using mechanical excavation equipment.

1.2 meters

300

This designated person must always be present when a worker enters a trench, acting as a safety watch and communicating with workers below. What is this person called?

A topman.

400

Supports must be installed at intervals no greater than how many metres, unless an engineer specifies otherwise?

1.5 metres / 4.9 ft

400

For Type 2 or 3 soil, what is the required slope ratio? (if you choose to slope)

1:1 (45 degrees). Equates to a 1 meter horizontal distance for every 1 meter of vertical rise

400

The minimum height a support system, such as shoring or a trench box, must extend above the top edge of an excavation, unless engineer drawings say otherwise?

0.3 metres / 0.9 ft / 11.8 inches

400

This is the minimum distance you must maintain from an EXPOSED utility when using mechanical excavation equipment.

0.3 meters

400

Spotters are mandatory when (give 3 major situations)

Reversing, Operating near underground utilities, operating near overhead utilities, around tree protection zones, in tight workspaces

500

Shoring boxes must be installed how close to the bottom of the trench, unless the manufacturer or engineer specifies otherwise?

No more than 1 foot gap / 0.3 m

500

For Type 4 soil, what slope ratio is required? (if you choose to slope)

1:3. Equates to a 3 meter horizontal distance for every 1 meter of vertical rise

500

Excavations exceeding this depth must be protected with a barrier or guardrail at least 1.1 meters (3.6 feet) high to prevent falls.

What is 2.4 meters or 7.9 feet?

500

Name 5 situations where work must be stopped immediately and the Utilities Coordinator (Jessica) must be notified for relocates.

-The drawing does not match the written locate area
-A utility shown on the locates is not found
-A utility is found outside the 1 m tolerance zone
-A utility is found but is not shown on the locates
-The utility found does not match the locate description (material, size, or service)

500

Under Rabcon’s rules, which soil types do we never classify soil as (to take the most precaution)?

Type 1 or Type 2