WA L&I + OSHA
Jobsite Hazards & Controls
Concrete
Project Management
Field Coordination
100

What is the minimum trench depth requiring protective systems under WA L&I?

4 feet (WAC 296-155-657)

100

“Danger” signs feature these two colors.

Red + White

100

This test measures the workability of concrete.

slump test (ASTM C-143)

100

This organizational system defines divisions and spec numbers.

CSI MasterFormat

100

Exposed vertical rebar under six feet must have these for impalement protection

What are rebar caps or covers

200

What are the four leading causes of construction fatalities in Washington? (Fatal Four)

Falls, struck-by, electrocution, caught-in/between

200

These short safety meetings should occur weekly according to best practice.

toolbox talks

200

Concrete should typically cure this long before full design strength.

28 days

200

This milestone marks when the project can be used for its intended purpose.

What is substantial completion

200

These steel boxes prevent trench wall collapses

trench boxes

300

What is the minimum distance a crane must maintain from energized power lines up to 50 kV in Washington?

10 feet (WAC 296-155-53408)

300

An excavation must have one of these individuals present whenever workers are inside.

a competent person

300

Concrete should be kept above this temperature while curing.

50 degrees

300

This document breaks down contract value by work item

Schedule of Values

300

You must call this number at least 48 hours before digging

811 (Call Before You Dig)

400

This color combination is used for “Caution” safety signs.

What are yellow with black letters

400

Training for bloodborne pathogens must occur this often.

Annually

400

Control joints are typically cut within this time window after finishing.  

6-12 hours

400

This analysis reduces cost while maintaining performance

What is value engineering

400

This sling angle is the minimum recommended for safe lifting

30 degrees from horizontal

500

Class A fire extinguishers must be within this travel distance.

75 feet

500

This WAC section governs fall-protection requirements.

WAC 296-880

500

The white salt-like residue appearing on concrete surfaces is called this.

What is efflorescence

500

Washington public projects hold this 5 percent portion until acceptance

retainage

500

This plan outlines erosion and runoff controls on site

Storm Water Pollution Prevention Plan (SWPPP)