Knowledge Areas
The Basics
More details
True or False
Let's get together
100

What does an acquisition Strategy address?

Program/Acquisition Title 

Acquisition Background

Plan of Action (sources, competition, funding, etc.) Contract Type

RISKS—and how they will be mitigated

Milestones/Schedule

Identification of participants in Acq Plan preparation

100

What is the purpose of acquisition planning?

To ensure the Government meets its needs in the most effective, economical and timely manner

100

What document is recommended if the estimated value is under the requirement for a formal acquisition plan?

A Streamlined Acquisition Strategy Summary (SASS) is recommended for other acquisitions

100

An Acq plan can be waived?  True or false

Bonus:  Who has the authority to waive it?

True

ASP Chairperson

100

What is consolidation?

Combining two or more requirements that have previously been contracted for separately into one contract

200

Where would you find the approval authorities for acquisition plans?

PEO Systems - AFI 63-101

PEO Services - AFI 63-138

200

When should acquisition planning begin?

As soon as the requirement is known

200

What are some actions that do not require an AP?

  • DoD Task/Delivery Orders IAW basic contract

  • Modifications within scope of contract

  • Replenishment parts (unless they require design; development; verification testing & approval before production)

  • Basic Research (funding category 6.1)

  • SBIR/STTR

  • Simplified Procedures for Certain Commercial Items covered in FAR Subpart 13.5

200

The ASP comes after the Acquisition plan.  True or False

FALSE

The ASP is always before the Acquisition plan

200

For consolidation, what is the threshold for approval and who approves?

If greater than $2M, shall coordinate with Small Business and approval authority is SCO

300

When is an ASP required?

When a formal Acquisition plan is required

300

An acquisition plan is developed by...?

Considered a “program document” however, needs to be developed by both the Requirements Owner AND Contracting Officer

300

Below the required thresholds, a formal AP should be considered for what types of actions?

  • Acquisitions with limited experience or moderate to high risks

  • Acquisitions with award/incentive fees

  • Acquisitions with a history of protests or performance problems

  • Acquisitions which use AFFARS 5315.3 Source Selection Procedures

300

An ASP can never be waived.  True or false

False

An ASP can be waived by the ASP Chairperson

300

What is bundling?

Bundling is combining 2 or more separate contracts into 1 contract when efforts were previously performed or could be performed by small businesses, but by bundling will make it unsuitable for award to a small business

400

Is there a more streamlined process for obtaining approval for a formal acquisition plan?  Explain the process

Combined AP/ASP

  • Allows the AP to be approved DURING the ASP briefing

  • MUST have signatures and all documentation otherwise contained in an AP

400

When is acquisition planning required?

Acquisition Planning is required for all acquisitions

400

If the ASP charts are used for the acquisition plan, what must me included?

All mandatory content from the FAR, DFARS, and AFFARS for an acquisition plan

400

AF PGI 5307.104-92 (b)(4) gives the CO the authority to sign an Acquisition Plan.  True or false

FALSE - AF PGI 5307.104-92(b)(4) “The acquisition strategy approving authority may utilize the ASP briefing charts and associated note pages, minutes, and changed charts to satisfy a required written AP if the content complies with requirements set forth in DFARS PGI 207.105”

400

Who is the approval authorities for bundling? and at what dollar values?

  • Approval authority is SPE

  • If substantial bundling (>$8M), CO shall coordinate with SB specialist who shall assist in identifying alternative strategies that would reduce or minimize the scope of the bundling

  • Send notification to current SB contractors of agency’s intent to bundle at least 30 days before solicitation

500

At what dollar values are acquisition plans required?

Development (R&D) >$10M

Production (supplies)/Services 

           >$50M for all years or

           >$25M for any Fiscal Year

500

Who is the approval authority for acq plan for operational and enterprise contracting?

SCO

500

What is needed if there are significant changes to the program?

A significant change to the program/acquisition requires a REVISED AP (and statement summarizing changes) be approved by the appropriate approval authority (AFFARS 5307.104-91)

500

Consolidation is a subset of bundling.  True or false

FALSE - Bundling is a subset of consolidation

500

What must be documented to justify consolidation?

Must always document the quantifiable benefits of consolidation