Job Costing
Labour Reporting
Procore
Detailed Expenses/ JC Reporting
Cost % of Completion
100

The primary purpose of a cost management system is...

A) To track costs accurately

B) To ensure timely payments

C) To monitor project progress

D) All of the above

What is D)


100

The day of the week in which the PM is responsible to send an updated field estimate and updated quantity back to the Financial Coordinator.

What is Thursday?

100

TRUE OR FALSE: 

All subcontractors going forward must be set up to bill their invoices in Procore.

What is TRUE.


100

TRUE OR FALSE:

If a cost code has been deactivated, a Change order can be spread to that code.

What is FALSE.

Once a cost code has been deactivated, you must reopen it if you want to spread more budget to that code.

100

This is the reason why tracking project P&L's is important.

A) To track financial performance and manage cash flow 

B) Identify areas of risk

C) Create/adjust long-term corporate goals

D) All of the above

What is D)


200

S A M P L E are all examples of this. 


What are Cost Types?


200

The highlighted numbers represent this types of data.

- Cost

- Percentage

- Hours 

200

TRUE OR FALSE: 

Subcontractors must pay invoices in Procore

WHAT IS FALSE.

As of right now, we are only required to have invoices set up only.  


200

TRUE OR FALSE:

If the payment terms of a contract are 30 days, we expect to be paid within 30 days.


What is TRUE.


200

This occurs when recognized revenue is less than the billed to date amount and is the main contributor to a positive cash position.


What is Overbilling?

300

TRUE OR FALSE:

Owners are typically billed for progress billings weekly. 

What is FALSE?

Progress billings are mostly sent out on a monthly basis


300

TRUE OR FALSE:

The field estimate % must be the same quantity % under each labour code.

What is FALSE?

They can be the same, but it is not necessary as quantity does not always reflect the % completion in terms of cost


300

RANDOM TRIVIA:

The largest project that Alberici is currently working on.

What is the Next Star Battery Plant in Windsor!

300

These are the goals of the monthly JC reporting review.

A) Updating additional costs to complete and projected total costs 

B) Communicating any outstanding issues and assessing risks and opportunities

C) Both A or B 

D) Neither A or B

What is C.

- Updating additional costs to complete and projected total costs 

- Communicating any outstanding issues and assessing risks and opportunities

300

This method recognizes revenue as work progresses on a contract or the percentage of the contract completed at a given time.


*2x POINTS IF YOU GET THE FORMULA*

What is the Cost Percentage of Completion Method?


=Actual Costs Incurred/Projected Total Cost at Completion

400

A written amendment to a contract signed by the owner and contractor upon a change in the scope of work is called this.


What is an Approved Change Order.


400

This is the correct order of the timeline to update labour reports.

A) Updated Field % to be returned to financial coordinator

B) New forecast entered and distributed with financial summary

C) Labour report is sent to PM to update the % complete

D) Payroll enters Hours


What is....

D) Payroll enters Hours

C) Labour report is sent to PM to update the % complete

A) Updated Field % to be returned to financial coordinator

B) New forecast entered and distributed with financial summary

400

FREE POINTS

FREE POINTS


400

This is NOT a use for the Detailed Expenses Report

A)  Comparing budgeted vs actual costs 

B) Forecasting future risks & opportunities

C)  Checking on the status of a code 

D) Seeing a list of active personnel on sight. 

What is D.

400

This occurs when recognized revenue is greater than the billed to date amount and is not good for cash. 

What is Underbilling?

500

A part of the Progress Billings that is updated by the Project Managers that states the percentage of work completed during the billing period. 

What is the Schedule of Value

500

This term is the new method being introduced to update quantity completion for each code in the field, as it automatically generates a field estimate % for labour codes.

What is the Rules of Credit method?

500

RANDOM TRIVIA:

The CEO of ACI.

ACL is Greg Brokenshire

ACI is Richard Jaggers!


500

There are 9 tabs in the Monthly JC Review Package 

Name 5 for 500

Name ALL for 1000. 

- Financial Summary/Dashboard

- Summary Report by Cost Type

- Summary of CO's

- Detailed Expenses Report

- Gross Margin 

- Bill Log

- Cash and Billings Curve

- Labour Data

- P&L


500

Name 3 Factors that Impact Revenue and Gross Margin

What is...