These are the 2 main foundations of Lean.
What is Continuous Improvement and Respect for People?
These are the people who are involved in the planning process. This includes superintendents, foreman, and/or general foreman
Who are the Last Planners?
The goal of phase planning is to focus on the _____ between activities.
What is handoffs?
15-20 minutes is the max time for this meeting.
What is a daily huddle?
This is the target percentage for PPC
What is 75%?
This pillar includes activities such as Team Health surveys and Owner Alignment session.
What is Team Building & Alignment?
This phase of LPS includes making reliable promises for next week's work.
What is Weekly Work Planning?
This is the recommended duration for a phase plan
What is 3-4 months?
This meeting happens on a weekly basis to solidify next weeks plan and conduct look ahead planning.
What is a WCM?
This is what PPC stands for.
What is Percent Plan Complete?
This pillar includes evaluating the process, behaviors, and physical conditions of a jobsite.
What is 5s & Waste Walks?
This phase of work includes establishing milestones, a baseline schedule, and flow
What is Project/Milestone Planning?
The traditional phase plan approach is to work backwards from the ______.
What is Milestone?
This person is responsible for running a daily huddle
Who is the superintendent?
Design, Material, Weather, Handoff-Other, and Workforce are all examples of this.
What is Variance Codes/Reasons?
The four additional foundations of lean thinking are optimize the whole, eliminate waste, focus on flow, and ___________.
What is Generate Value?
This phase of LPS includes specifying handoffs and flow.
Phase planning and ____ planning are synonymous with each other.
What is Pull?
These are the people expected to attend and participate in the WCM.
Who are the Last Planners?
Just like IIF, Lean is a _____change.
What is culture?
The main goal of all lean thinking and tools fall under this umbrella.
What is operational excellence?
What is Learning (Phase)?
The goal is to improve productivity with ______, transparency, optimization, and efficiency
What is collaboration?
Labor, Submittals, Inspections, and Shop Drawings are all example of this.
What is a constraint?
True or False: PPC is a way to track if you are on schedule
What is false?