Owners & Contractors
Project Manuals
B/A & Project Award
Construction
Potpourri
100

Capitalized terms, such as “Owner”, “Work”, and “Contract Sum/Price”, are defined terms in the ________________ Conditions.

General

100

Blank pages are normally inserted between sections that end in an ODD/EVEN page number?

ODD

100

True or False: All projects are advertised in newspapers.

FALSE

100

If no date is requested by the Contractor on an RFI, T&L will self-impose a deadline of ___ calendar days for review and return of the RFI to the Contractor.

7

100

How many office locations does T&L currently have?

8

200

What are the two types of bonds normally submitted by the Contractor with the signed Owner/Contractor agreement?

Performance & Payment Bonds

200

Technical specifications are comprised of Division __ - Division __.

02-49

200

What is the main planroom which T&L works with but which both RU and LU do not?

TRASCO

200

Review submittals should be reviewed within ___ calendar days and returned back to the Contractor.

15

200

True or False: An agency may be both a funding agency AND a regulatory agency on a single project.

TRUE

300

In AIA documents, insurance requirements are specified in the A101, Exhibit A document.  Where are insurance requirements specified in EJCDC documents?

Supplementary Conditions (SCs)

300

DEB does not allow the use of ________, but they do allow additive bid items.

alternates

300

Valley Construction News is included in the advertisement for a particular project.  Will this planroom receive a free electronic set of bid documents?

YES

Bonus: What other document should be emailed to Valley Construction News?

300

Contract times for a project are 120/150, which means ____________ completion should be completed within 120 calendar days and __________ completion should be completed within 150 days.

Substantial/Final

300
Which MasterFormat division are the front end documents found in?
Division 00


400

In this type of project, a Project Owner contracts directly with two parties (A/E and Contractor), whereas in Design-Build projects, the Owner contracts directly with only one party.

Design-Bid-Build

400

Changes to these two types of documents are shown in track changes because they are considered boilerplate documents.

AIA & EJCDC

400

Bids have been opened for a particular AIA project.  Can an addendum still be issued if the Owner/Contractor agreements have not yet been signed?

YES

400

An ________   __________ Review meeting is normally held as part of project closeout to debrief and discuss what went right and what went wrong.

After Action

400

DEB project codes are comprised of how many digits?

11

500

A Contractor is looking in a particular spec section for how to install a particular product.  Would he/she look in PART 1, PART 2, or PART 3 of the specification?

PART 3

Bonus: _____Format says that the specification is broken down into 3 PARTS.

500

These two types of documents include seals pages and drawings indexes.

AIA & DGS

500

TRUE or FALSE: T&L normally prepares a bid evaluation letter/package after bid opening to recommend award of each contract.

FALSE

500

Name the three types of change documents that are used to meet these criteria:

1.  Document minor changes in work

2.  Document changes in time and/or price

3.  Document anticipated changes in time and/or price but the particulars of which have not yet been determined.

1. ASIs/Field Orders

2. Change Orders

3. Work/Construction Change Directives

500

MasterFormat is comprised of how many total divisions?

50