Values and Principles
Roles and Responsibility

SCRUM Methodology
KANBAN Methodology
100

In Agile , working output is given importance over ?

A) comprehensive documentation

B) contract negotiation

C) following a plan

A) comprehensive documentation

100

Who assigns the work/tasks to the team members in Agile project?

Product Owner

Scrum Master

Chapter Leader

Team members self-assign the tasks

Team members self-assign the tasks

100

The maximum week limit for a Sprint is _____

2 weeks

3 weeks

4 weeks

5 weeks

4 Weeks

100

This performance metric is not used in Kanban

Velocity

Lead Time

Cycle Time

Average Cycle Time

Velocity

200

One of the Agile principles states the below

Build projects around ___________ individuals.
Give them the ___________ and support they need and trust them to get the job done.

A. specialized, tools
B. motivated, environment
C. technical, documentation
D. motivated, documentation

B) motivated, environment

200

______________ facilitates the ceremonies and removes impediments

Any team member

Product Owner

Scrum Master

Chapter Leader

Scrum Master

200

Squad leader's role is a combination of which 2 roles ?


Product Owner

Product Manager 

200

What happens when the Kanban Work In Progress (WIP) limit is not being honored ?

Team throughput increases.

Processes will suffer from inefficiency

Concurrent operations will slow down.

Feedback loops will be shorter

Processes will suffer from inefficiency