Contracts
100

Name the contract that provides the General Conditions of the Contract for Construction

AIA A201

200

The AIA B201 is The Standard Form of Agreement Between the _____ and _____

Owner and Architect

300

This document is used to implement changes agreed upon by the owner, contractor, and architect; often involving changes in scope, cost, or schedule.

Change Order

400

Stage in a construction project when the work is sufficiently complete for the owner to use the building for its intended purpose

Substantial Completion

500

Portion of the contract payment withheld until the project is substantially complete to ensure the contractor completes the work properly

Retainage