Inputs
Outputs
Tools and Technique
Determinen Earned Value
Performing Cost Analysis/schedule analysis

100

This Includes cost baseline, project management plan. And work performance.  This is an example of?

Control cost Inputs examples

100

weekly project status updates posted to all stakeholders and sponsors 

Project management plan updates 

100

Earned value management

Measure the success of a project due to actions

100

The value of the work that should have been completed at a specific point in time, except any work started ahead of schedule.

Planned Value (PV)

100

the difference between the actual cost incurred and the planned/budgeted cost at a given time on a project.

Cost Variance.

200

There are two types of requirements. Total funding requirements and project requirements This is an example of?

Project Funding Managing requirements 

200

 project budget is $350,000, a project manager may study spending costs and forecast the project to stay under budget by $100,000.

Cost forecast 

200

Forecasting

estimates the future project performances

200

The cost of the work that has been completed at a specific point in time, including any work started ahead of schedule.

Actual Cost (AC)

200

a metric used to determine if tasks within a project use up more or less of the budget assigned to that project

Cost Performance Index

300

what is the schedules progress? or how much of the work is being completed? These are questionnaire example of what?

Work performance data 

300

This includes. Cost performance, money spent. and schedule performance 

Work performance information

300

Schedule and Cost Analysis

The work completed vs. the time or cost of work to be done

300

A estimate of the progress of a project and the basis for cost analysis, including any work started ahead of schedule.

Earned Value (EV)

300

a measure of the conformance of actual progress (earned value) to the planned progress

Schedule Performance Index

400

When you're analyzing and managing cost, the project manager can influence and manage changes related to cost. What is this called?

Controlling cost 

400

A document used to adjust the project which can outturn how we control the cost. Is called what?

Change request

400

To-complete 

The work needed from resources to reach the cost goal and their deadline

400

Total the value of each project activity scheduled for completion at a specific point in time.  

$60,000

Planned Value Calculation/Amount

400

the difference between the percentage of work completed versus the percentage expected to be completed by a particular date.

Schedule Variance

500

Project Mangement, Work performance data, Project funding requirements, and organizational are all examples of ?

Control Cost inputs 

500

 this is an estimation of cost relating to how much the project or products will cost Is called what?

Cost forecast

500

TOTAL ALL THE PROJECTS COSTS AT A SPECIFIC POINT IN TIME: 

$80,000

This is an example of whhat

Actual cost calculation / amount 

500

What term do these formulas belong to?  1.(CPI = EV / AC ) 2.(SPI = EV / PV)

1.cost performance index

2.Schedule Performance Index