100

Responsible to ensure customer is satisfied, and scope of project is completed in timely, quality manner

Project Manager

100

In a network diagram, the path of activities that has the lowest value for total slack.

Critical Path

100

This describes the participation by various organizations people, and roles in completing tasks and deliverables for a project

Responsibility assignment matrix.

100

Reporting system to distinguish between accomplishments and busy work

Management Information system

100

Project funding annoncement posted by an organization for which companies place bids

Request for Proposal

200

A bar chart for planning and scheduling

Gantt chart

200

A measure that is used to quantify the amount of variation or dispersion in a set of data values, expressed as a quantity defining how much the data is dispersed about the mean

Standard deviation

200

Successful Project Managers use ____________ and  ___________ while fostering motivation through ___________.

Participative

Consultative

Positive reinforcement.

200

A techniques in which start and finish dates/times are adjusted based on resource limitations with the goal of balancing demand for resources with the available supply.

Resource leveling

200

Amount of Time a task can be delayed before the project finish date is delayed

Total Slack

300

Opposite of wait and see approach

Pro-Active.

300

LF - Estimated Duration

Latest start time

300

Recognition and appreciation of team members by project Manager

Motivation.

300

Units of related tasks which are used to break projects up into smaller sections in a work breakdown structure

Work Package

300

At the start of the project Project managers need to establish a ___________  ______________ _______ to define how changes will be ____________

______________ and ______________.

Change control system

documented 

approved

communicated