Ground Mount
Trenching
Detached Structures
Meters
True or False?
100

What should the rotation of the Ground Mount system be set at in Aurora?

What is: 180 degrees (south facing)

100

How much of the potential trenching is covered by Everlight?

What is: 70 ft.

100

If a detached garage/shed is not a far distance from the house (next door/backyard), would we need to draw a potential trenching path?

What is:

Yes, always👍

100

What do we call a system with panels on both the house and a ground mount system?

What is:
Hybrid System

100

True or False:
There is a limit to how many panel columns we can include in a ground mount system before splitting into separate ground mounts.

What is: False, no limit

200

How far should we place Ground Mount systems away from fences, gates, or property lines?

What is: 10 ft.

200

What can we NOT trench through?

What is: Driveways/Concrete

200

Scenario: This opp has the option to place panels on both the house and the detached shed. Where would we prioritize placing panels first based on the layout below? 👇


What is:
The shed (Still prioritizing southern exposure, in this case, the shed is preferred with lots of room on the SE roof face and minimal shading)

200

When working on an opp with multiple meters, what needs to be done in SalesForce?

What is:
Check "Electrical Upgrade" box under System Add Ons and communicate to EC in SF chatter.

200

True or False:
We can install this ground mount system.

What is:
False, ground mount systems are 4 rows high (no more/no less).

300

For a ground mount system with Alliant, if a system will produce at either 88% or 108% (since we can’t reduce panels by just one), which option would we go with?

What is: 108% (and report at 98%)

300

Which would be preferred as a potential trenching path?

A:


B:

A: 

300

Can we install this layout on a detached structure (MN)?

What is:
 Yes, we can ignore setbacks on detached structures!

300

During the design review process, you are made aware of the exact location of the meter. Should you adjust your potential trenching path to reflect the exact location?

What is:
Yes, adjust your proposed trenching path to be as accurate as possible. 

300

True or False:
In the event that there are two meters on a duplex, we do a meter consolidation.

What is:
False
("bonus" available if you can explain why ( ͡° ͜ʖ ͡°) ) 

400

Ground Mount systems are a minimum of ___ rows high.

What is: Fo' (4)

400

Which would be preferred as a potential trenching path?


A:

B:

B:

400

Can we install this layout on a detached structure (MN)?




What is:
Yes, we can ignore setbacks on detached structures!

400

Working with an opp that has multiple meters and separate graphs for each one, how would we go about inputting the usage into Aurora?

What is: Combine the kWh from both graphs into Aurora.

400

True or False:

Based on the info provided in the design notes for this opp, meter consolidation is needed.

What is: False

500

What is the tilt and panel orientation of a Ground Mount system?

What is: 26 degree tilt and landscape orientation.

500

Which would be preferred as a potential trenching path?

A:

B:

B:

500

Scenario: This opp has the option to place panels on both the house and the detached shed. Assuming both of these layouts produce the same and both systems utilize the same number of panels. Which would be the preferred option?


A:

B:

B:

500

How should the one-line look for Xcel Solar Rewards?

What is:
The one-line should reflect:
Net Meter --> AC Disco --> PV Disco --> Combiner

500

True or False:
The customer has already trenched to connect the detached structure, so no trenching is needed.

What is: False (trenching always)