If the pressure-relieving device is of insufficient capacity what must be done?
A new or additional device must be installed, or the regulator(s) must be modified or replaced to provide the additional capacity required.
Who signed final approval for Technical Standard G-OM1037?
Mike Kisicki
Town Border Station meters can what 2 styles?
Rotary
Turbine
All district regulator station and supplier’s relief devices will be reviewed and capacities will be calculated at intervals not exceeding?
15 months, but at least each calendar year. Required capacities will be compared with rated capacities.
Set Points on Reliefs are required for what main reason?
So that the maximum allowable operating pressure will not be exceeded.
What Federal DOT Safety standard covers "Required Capacity Of Pressure Relieving And Limiting Stations"?
192.201
Found in Technical Standard G-DN2003 (Page 3)
Completed inspection forms will be retained in GasValve for review and reporting for _______ years.
10 Years
All components of a pressure regulator station upstream of a pressure-regulating device must have the same or greater MAOP as
Inlet Station Piping
When an elbow is used to direct a horizontally venting relief valve to the vertical, how large of weep hole is required and why?
Install a 1/8" weep hole in the elbow to ensure that the vent stack does not fill with water.
What's the newest effective date of OM 37?
4/1/2017
What database does the company use for Scheduling and Permanently recording each annual scheduled test and inspection?
Gas Valve
Approved Town Border Stations generally consist of what 4 items?
- measurement
- pressure control
- overpressure protection
- odorizer equipment
Found in Technical Standard G-DN2003 (Page 4)
What 7 items are required to verify when inspecting a Relief Valve at its yearly inspection?
- Good mechanical condition
- The proper set point [192.739(c)]
- Actuate the "main" valve piston in addition to the pilot.
- Unobstructed vent line
- Protective devices installed to prevent entrance of moisture, dirt, or other conditions that might prevent proper operation
- A properly supported and protected control line
- Adequate capacity and reliability, of operation, for the service for which it was designed
The Company is responsible for ensuring that all work completed by its consultants and contractors complies with?
Federal and State regulations and the Company’s operating procedures.
DOUBLE JEOPARDY
Regulatory requirements applicable to the design of Town Border Stations are found where?
In 49 CFR Part 192, State Codes, and in NFPA 54.
(Found in Technical Standard G-DN2003 / Page 3)