What does SCC stand for in change control numbering system?
System
What are the three types of changes?
Temporary, permanent and changes in ancillary documents
What is the target implementation time for change proposals after their initiation in Caliber QAMS?
30 working days
What is the maximum number of extensions allowed for the initial target completion date of a change control?
Two
Which type of change reverts back to normal procedures after a defined period?
Temporary change
Who is responsible for initiating a proposal for change?
The Originating Department Head
What is the primary purpose of Change Control in a Quality Management System?
To ensure changes are made in a controlled manner, maintaining product quality and compliance
When should notification to the customer occur in the change management process?
If the first system change control in 2020 is initiated, what would its format be?
SCC-El-20-0001
In the change control numbering system, what does LL represent?
Encube location code - E1 for goa plant