Who will be always the pilot if the change is during the project?

The Project Manager

100

Meaning of Abbreviation ECR…

Engineering Change Request

100

How many Steps has the Life Cycle of an ECR on PDM?

7 Steps

100

Meaning of Abbreviation ECO…

Engineering Change Order

100

Meaning of Abbreviation PDM…

Product Data Management

200

A Modification of a packaging should be managed by CLI02-01-003?

Yes

200

True or False: If there is no Parts or no CAD Documents impacted by the modification, ECO is not needed?

True

200
According to which operating instruction the audit to close the change must be done?

According to MAN02-03-003

200

True or False: 

During Design Phase (before tooling Kick Off) the usage of ECR is not mandatory but possible?

True

200

New tools should be managed by CLI02-01-003?

Yes

300

At what step of an ECR the decision is taken?

Step 4

REVIEW of the Impact analysis and risks for decision

300

Can be cancelled an ECR in CREATE status?

No, it must be at least in Submit.

300

Who takes the decision of manage the change with QP or action plan?

The decision is taken by the PLM at the status “REVIEW” and record in the ECR before the kickoff.

300

How many Steps has the Life Cycle of an ECO on PDM?

6 Steps

300

At what step of an ECR the Actions are defined?

Step 5 Plan ECO: Action plan & Review

400

The impact analysis is done at what step of the ECR?

STEP 3

STATUS EVALUATE: Evaluate the impacts and risks

400

True of False: 

One ECR can be connected to several ECO?

True - For multiple components, several use cases.

400

Who appoints the pilot of the change AFTER the project end by a change managed by PL?

The PLM

400

True or False: 

The changes managed with a quality plan are not always followed in project steering committee – CPP.

False - Are always followed in project steering committee – CPP. (see CLI02-01-005)

400

Who appoints the pilot of the change AFTER the project end by a change managed by Technical Group?

The Technical Manager.

500

How is decided if the change is managed by Product Line or by Technical group?

By answering the questions in the ECR template

500

Who is the ECO approve to promote to Released state?

The Project Manager

500

Which are the mandatory Elements in Action Plan of an ECR?

The action plan must contain at least an industrial production, an audit including the document checking of PSW dossier.

500

Who approve the Step Review of an ECO?

DE & PE approvals

500

Who validates and perform the closing review of a PL change AFTER Project end?

PLM /Engineering manager + PQE