Procurement Requirements, Pt. 1
Procurement Requirements, Part 2
Contracting Requirements, Part 1
Contracting Requirements, Part 2
Miscellaneous
100

The Bidding stuff

What are Procurement Requirements?

100

AIA document commonly used to provide instructions to bidders; also include the AIA document number

What is AIA A701-Instructions for Bidders?

100

This is the typical Agreement (or Contract)  for construction

AIA A101: Contract between Owner & CM/GC for a Stipulated Sum

100

According to AIA A201, Drawings & Specs act as one document or one volume of information, and what is required by one, shall be as if required by the other.......name this formal relationship.

What is "Complementary" ?

100

This item breaks down the entire construction contract into smaller scopes of work based on Subcontractor scopes, or spec sections of work

What is the Schedule of Value 

NOTE: SOV must be APPROVED by the A/E prior to use on the project (or applied to Applications for Payment).

200

A public announcement by the Owner of a construction project which is available for competitive bidding purposes

What is a Solicitation?

200

This item modifies, changes, adds to, or deletes from a commonly issued standard or stock document (like A701)

(Hint: This is not an Addendum)

What is a Supplement (or Supplemental Information)?

200

This is the type of contract referenced above (AIA 101)

Stipulated Sum (or Lump Sum)

1 contract price for 1 scope of work (or the entire project)

200

The Drawings, Specs & Addendum are "what" is to be built by the CM/GC......but AIA A201 describes the "How" the project is built.......name this "How" the project is built (as described by A201).

What is the "Means & Methods" for the project?

(All are the responsibility of the CM/GC).

200

This value (approx. 5-10%) is withheld by the Owner from each monthly Application for Payment.....why?

What is the Retainage?

The Owner withholds a small portion of the Payment (5 or 10%) so the CM/GC will complete all aspects of the Contract Requirements .......once the "Contract" is 100% complete, the Owner will return the withheld Retainage amount.

300

Advertisement for Bidders, Invitation to Bid, or Request for Proposals

What are typical titles of a Solicitation?

300

These are the most common items included in Available Information

What are the following:

1. Soil Borings Report

2. WBO: Work By the Owner

300

These are the 2 parts of the required Construction Bonds; also include the AIA document number

What are the Payment Bond & the Performance Bond? (AIA A312)

300

The CM/GC & the A/E are communicating throughout the entire construction project process.......name this Q & A process

Question: 

RFI-Request for Information

Answer: 

ASI-Architects Supplemental Information (or Instructions)

300

These are the typical dispositions for each & every Product Submittal processed for the construction project.....name all 4.

What are:

1. Reviewed w/ No Comments

2. Review w/ Comments (The "Comment" may be the product color selection)

3. Revise & Resubmit (Not good)

4. REJECTED (even worse)

NOTE: CM/GC barely have enough time to process the Submittals once......definitely not enough time & money to repeat the process again........

400

This is the typical value for the Bid Security

What is usually between 5-10% of the Bid value?

400

This is the common Bid Form used for public, competitive bid projects in the State of Indiana

What is Bid Form 96?

400

This is the minimum value of the Construction Bonds

The minimum value is the full value of the construction contract (or 100% of the construction contract value)....again, usually a minimum value.

400

This is a Temporary Change Order

What is the CCD: Construction Change Directive?

400

The original Bidding Documents (the Drawings, Specs & Addendum) are what is intended to be built by the CM/GC.......what is the title of the documents that describe how the project WAS actually built.....these include all modifications made during construction.

What are the Project Record Documents (sometimes incorrectly referred to as "As-Builts" )?

500

This is the most common Bid Security

What is the Bid Bond?

500

These are commonly included "Supplements to the Bid Form"

What are the following:

1. Acknowledgement to the Receipt of Addendum

2. Acknowledging the use of Liquidated Damages (beginning on the DOSC: Date of Substantial Completion)

3. Alternate Bids

4. Unit Price Bids 

5. Subcontractors List

6. Requested Products to be used on the Project

7. Approval by the State of Indiana for public Bidding

8. Requirements for use of Minority Ownership companies, et al......

500

The General Conditions of the Construction Contract provide general information about how the construction contract is completed......name these 4 R's of the General Conditions.

The 4 R's of the General Conditions are as follows:

1. Rights

2. Roles

3. Responsibilities

4. Relationships

And how these affect each Contractual party....which includes the Owner, A/E, CM/GS & Subcontractors.

500

True or False

Every change or modification to the construction project requires a written Change Order? (Careful)

FALSE

Only changes in scope that affect either construction time (or the DOSC), or construction value ($$) of the contract, require a formal Change Order.

500

Titles of the follow Division 01 Spec sections:

01 20 00

01 30 00

01 40 00

01 50 00

01 70 00

What are as follows:

01 20 00: Price & Payment Procedures

01 30 00: Administrative Requirements

01 40 00: QA/QC Requirements

01 50 00: Temporary Facilities & Controls

01 70 00: Project Closeout Requirements