SITE LAYOUT PLAN, UTILITIES & FOUNDATION
STRUCTURAL: METHODS, SEQUENCE, SCHEDULING
ARCH QTO & SOLIBRI
NAVISWORKS
CONSTRUCTIBILITY ISSUES
100
Occupational Safety and Health Administration
What does the acronym OSHA stand for?
100
Gradall, Mobile Crane, Manlift, Truck Crane
What piece(s) of equipment would be useful during steel erection?
100
.IFC
What file type extension does Solibri Model Checker open?
100
Frames Per Second
What does the acronym "FPS" in the Export Animation box for Autodesk's Navisworks Timeliner stand for?
100
.NWF
What is the live, working Navisworks file?
200
Storm Water Pollution Prevention Plan
What does the acronym SWPPP stand for?
200
6 Week look-ahead schedule
What is a short-interval schedule that included 1 back week, the current week, and four forward weeks?
200
Export to .IFC
How do you get the desired file type from Autodesk's Revit to use in Solibri Model Checker?
200
Constructibility
What does a Timeliner model viewed in a desired sequence allow you to visually check for?
200
GC
If an issue or clash is NOT on the Constructibilty Summary Report, who owns the issue?
300
GAS, ELECTRIC, SANITARY, WATER
What temporary utilities may be provided at a construction site?
300
Method Analysis
What term is defined by detailing "what to do" during a construction's activity?
300
You must click "Takeoff All" again to update the Takeoff Report
If you change a column or alter the information of the Quanity Takeoff in the Solibri Model Checker software, which of the following is true?
300
Rules Tab
What Clash Detective tab allows you to minimize false clashes by adding, editing and deleting rules?
300
RFI's, Change Orders, Payment Request Reviews, Punch List
Once the Contract Administration phase begins, what document(s) is the architect responsible for delivering?
400
X,Y,Z Coordinates in Units and Transform Dialogue Box
What is one of the first aspects to check when using Autodesk's Navisworks after receiving plans/models from a subcontractor, architect, etc.?
400
Method Analysis, Sequencing, Schedule Analysis
What are the correct activities for analyzing the erection of the steel components of a building?
400
Waste Factor
What is the difference between material purchased and material installed?
400
DWF
When exporting a Revit model to a Navisworks file, what is the appropriate file format?
400
Prepare Program and conceptual drawings
During Schematic Design Development, the Architect will?
500
Visibility Graphics
What tool should be utilized when you want to turn "on" or "off" components in Audodesk's Revit?
500
Simulate
What is the Autodesk's Navisworks Timeliner tab is used to animate the schedule?
500
Checking
If you want to "Launch Checking" and "Create Reports" while working with Solibri Model Checker software, which View will you use?
500
Timeliner Simulation
If you wanted to export the complete animation from Autodesk's Navisworks Timeliner, what would you select as the source type?
500
Cost, Schedule, Scope of Work
What are Global Implication(s)?