Identifies the responsibility, accountability for each segment of work
What is the OBS?
The two components that make up an EAC
What are ACWP + ETC?
The Cost Performance Index (CPI) is a measure of:
What is cost efficiency?
The preferred relationship type used in the IMS
What is Finish to Start?
The tool used to record corrective actions
What is Empower?
All approved Schedules, budgets, work authorization, and cost collection is considered
What is the Performance Measurement Baseline (PMB)?
Monthly EAC analysis should consider _____ along with the remaining quantities, resources, and risk
What is CPI?
The earned value method where BCWP equals BCWS
What is LOE?
The currently approved time phased plan for executing work
What is the Baseline?
Target duration for corrective actions to be addressed
What is 30 days?
A direct representation of all authorized work scope on the project
What is the WBS?
Realization hours on LOE staffing plans are used to ______
What is to calculate the manhours per period?
What is the SPI most probably going to be at the end of a project
What is 1.0?
The IMS must be developed with integration through these two structures.
What is the WBS and OBS?
Corrective actions are recorded where
Where is the VAR and the VAR corrective action log?
The organization or function responsible for controlling indirect Cost
Who is F&A (CFO or Accounting)?
Supplemental detail required with TLSM classification of % complete, Weighted Milestone, or Units Complete
What is a Quantifiable backup data (QBD)?
A WP using 0/100 TLSM is reported at 95% complete – What is its earned value
What is zero?
What this represents in the schedule:
What is behind baseline and on critical path?
The two fields to be updated when actions take multiple periods to complete
What are % complete and Due Date?
The integration of the ___ and ___ creates the control account and facilitates the schedule and cost performance measure
What is the WBS and OBS?
Monthly EACs should be timely, accurate, reliable and ________
What is auditable?
If CPI is 0.85 and TCPI is 1.25 for a control acct – then future performance must be ________ than in the past
What is more efficient/better?
** Daily Double **
The definition of total float
The term used by the CAM at the point the corrective action has been completed
What is Submitted?