100

These preliminary studies involve the procurement, analysis and use of secondary information gathered for the project to aid the Client in early decision-making. 

Pre-Feasibility

100

The architect evaluates owner's program, schedule, budget, project site and proposes methods of project deliveries. What phase is this?

Schematic Design Phase

100

How many specialized architectural services are specified under SPP 203?

23

100

SPP 204 B is what service?

Construction Management Services

100

How many main services are there in SPP 205?

2 (Building and Facilities Admin, Post-Construction Evaluation)

200

It incorporates a space program with characterizations of the envisioned spaces such as ambiance, cost range, etc.

Architectural Programming

200
In this phase, the architect review and refine the requirements and translates them into architectural program.

Project Definition Phase

200

It is concerned with the general quality of the settings for the people and their activities, buildings and other natural and man-made phenomenon.

Physical Planning

200

The ________ is directly and professionally responsible and liable for the construction supervision of the project. 

AICC

200

An architect is brought in to evaluate which areas of a hospital parking garage need structural repair and waterproofing work. What service is this? 

Building Maintenance

300

An analysis of the space requirements of the project based on organizational structure and functional set-up. 

Space Management Studies

300

In what phase does the architect assists the owner in filing the required documents to secure approval of government authorities having jurisdiction over the design of the project?

Contract Document Phase

300

The architect in this area of practice engages in methods of producing building components in a highly engineered, efficient and cost-effective manner, particularly for residential and commercial applications. 

Building Systems Design

300

The CM reviews the master schedule and notices the ceramic tile installation is slated to begin prior to waterproofing being completed in the bathrooms. The CM directs the contractor to re-sequence the activities.What scope of service is this?

Coordination and Supervision

300

What service is where the architect determines the effectiveness of the various building systems and the material systems is use?. 

Post-Construction Evaluation

400

The goal of this service is to achieve an unimpaired program at minimum cost.

Value Management

400

What type of specifications should be submitted during design development phase?

Outline Specifications

400

This type of specialized services include determination as to the cause of the deterioration of the building, its component, or its materials as well as the causes of the observed deficiencies of the building

Forensic Architecture

400

Who are the four principal members involved in the design and building construction process? 

Owner, Architect & Consultants, Contractor and/or Subcontractor, Construction Workers

400

Give the four services under the Building and Facilites Admin. 

Building Maintenance, Grounds and Landscaping Supervision, Building Equipment Maintenance and Building Development and Management. 

500

Projects may require this kind of services in order to develop and generate financial support and acceptance from governing agencies or from the general public.

Promotional Services

500
What phase in SPP 202 where the architect shall not be required to make exhaustive on-site supervision to check on the quality of the work involved. 

Construction Phase

500

How many percent of the cost of work is paid for the architect who renders Architectural Interiors?

15%

500

When projects are still manageable in size, the architect was then assisted by a construction inspector, traditionally called ___________?

Clerk-of-Works

500

The rate of an architect's fee is from _____% of gross rentals?

4%-6%